Home > Forecasts & Analysis > Congressional Response > Derivatives and Risk Management > Appendix B: Details of Present Net Value Calculation

Derivatives and Risk Management in the Petroleum, Natural Gas, and Electricity Industries
 

Appendix B: Details of Present Net Value Calculation

Economics of New Combined-Cycle Generator

This appendix describes in more detail the calculations of net present value (NPV) reported in Chapter 2. The combined-cycle (CC) generator example is particularly relevant because the technology is less capital intensive than other technologies, such as coal, nuclear, and renewable electricity plants. In addition, Energy Information Administration projections show natural-gas-fired generation increasing from 16 percent of total U.S. electricity generation in 2000 to 32 percent of the total in 2020, overtaking nuclear power as the Nation’s second-largest source of electricity by 2004.150 Moreover, a growing number of refineries, petrochemical plants, and other industrial facilities that use natural gas to generate electricity for their own needs are becoming cogenerators, selling excess electricity to local utilities and power marketers. Those firms rely on stable natural gas supplies and prices; volatile gas prices can have considerable impact on their earnings, as noted in Chapter 2.

Capital Budgeting for a Power Generator

In the example shown in Chapter 2, an independent power producer faces a capital budgeting project (e.g., building a gas-fired plant) and uses NPV methodology to evaluate the project. The simple rule often given for choosing investment projects is the NPV rule: choose only projects with positive NPVs. The NPV methodology implicitly assumes that the incremental cash flows from a project will be reinvested to earn the firm’s risk-adjusted required rate of return throughout the life of the project. The NPV of a project reveals the amount by which its productive value (present value of net cash flows) exceeds or is less than its cost. Naturally, investors choose only those projects whose productive values exceed or at least equal their costs. If the NPV of a project is positive (NPV > 0), the amount of the NPV is the amount by which the project will increase the value of the firm making the investment.

The assumptions underlying the capital investment example shown in Chapter 2, Table 4, are summarized in Table B1.151 Table B2 shows the detailed annual cash flow calculations based on the assumptions and the price projections shown in Chapter 2, Table 4. Because the plant has a positive NPV of $2,118,017, it is profitable and should be built.

NPV Distributions with Simulation

In fact, the future output and input prices for the project are uncertain, and it may become unprofitable if the actual input and output prices vary much from their expected means. Therefore, a Monte Carlo simulation was used to estimate the distribution of the project’s NPV when both electricity and natural gas prices are varied.152 For the simulation analysis, lognormal distributions were defined for both electricity and natural gas prices, and the prices were varied by plus and minus 77 percent and 47 percent, respectively, as a standard deviation, from the expected prices.153 The price variations were based on daily historical data on NYMEX spot prices from March 1999 through March 2002. A historical positive correlation of 0.88 between the average electricity spot price and Henry Hub natural gas spot price was specified for each year of the project’s life.154 The NPV distribution generated by the simulation is shown Figure 6, and the statistical results and summary are shown Table 5, in Chapter 2.155 The simulation results indicate that there is about a 17-percent chance that the investment will be unprofitable (i.e., that it will have a negative NPV).

Figure B1.  NPV Simulation with Hedging for Input and Output Price Volatilities.  For more detailed information, contact the National Energy Information Center at (202) 586-8800.

Because the investor faces some probability of loss as a result of price fluctuations, he may have an incentive to mitigate the risk by hedging with such tools as long-term contracts, futures, options, and swaps. It was assumed for the analysis that the power producer’s maximum risk tolerance for the price volatilities was plus or minus one standard deviation from their means, or 77 percent and 47 percent of the mean price for electricity and natural gas, respectively. This assumption led to triangular distributions for both prices (Table B3).

When it was assumed that the price volatility would be hedged, the probability of positive NPV increased from 83 percent to 99 percent with a coefficient of variation (CV) of 0.42. Without hedging the price volatility, the CV was 1.09. The distribution is shown in Figure B1. The summary of statistical results and a statistical comparison of the simulations are shown in Table B4. As shown, a hedged project has less probability of negative NPV, smaller standard deviation of NPV, and a smaller risk measurement (CV).

 

Appendix B - Tables

Sources