Because analyses by EIA are required to be policy-neutral, the projections
in AEO2007 generally are based on Federal and State laws and regulations
in effect on or before October 31, 2006 (although there are exceptions
to this rule, as discussed below). The potential impacts of pending or
proposed legislation, regulations, and standardsor of sections of legislation
that have been enacted but that require implementing regulations or appropriation
of funds that are not provided or specified in the legislation itselfare
not reflected in the projections.
Selected examples of Federal and State legislation incorporated in the
projections include the following:
- The new CAFE standards finalized in March 2006, which establish higher
minimum fuel economy performance requirements by vehicle footprint for
light-duty trucks
- EPACT2005, which includes mandatory energy conservation standards; creates
numerous tax credits for businesses and individuals; creates an RFS and
eliminates the oxygen content requirement; extends royalty relief for offshore
oil and natural gas producers; and extends and expands the PTC for electricity
generated from renewable fuels
- The Military Construction Appropriations Act of 2005, which contains provisions
to support construction of the Alaska natural gas pipeline, including Federal
loan guarantees during construction
- The Working Families Tax Relief Act of 2004, which includes tax deductions
for qualified clean-fuel and electric vehicles; and changes in the rules
governing oil and natural gas well depletion
- The American Jobs Creation Act of 2004, which includes incentives and tax
credits for biodiesel fuels and a modified depreciation schedule for the
Alaska natural gas pipeline
- The Maritime Security Act of 2002, which amended the Deepwater Port Act
of 1974 to include offshore natural gas facilities
- State RPS programs, including the California RPS passed on September 12,
2002
- The Clean Air Act Amendments of 1990 (CAAA90), which included new standards
for motor gasoline and diesel fuel and for heavy-duty vehicle emissions
- The National Appliance Energy Conservation Act of 1987
- State programs for restructuring of the electricity industry.
AEO2007 assumes that State taxes on gasoline, diesel, jet fuel, and E85
[4] will increase with inflation and that Federal taxes on those fuels
will remain at the nominal rate established in 2003 (the last time the
Federal taxes were changed). AEO2007 also assumes that the ethanol tax
credit, as modified under the American Jobs Creation Act of 2004, will
be extended when it expires in 2010 and will remain in force indefinitely.
Although the ethanol tax credit includes a sunset clause that limits
its duration, historically it has been extended regularly, and AEO2007 assumes its continuation throughout the projection [5]. AEO2007 also includes
the biodiesel tax credits that were created under the American Jobs Creation
Act and extended through 2008 under EPACT2005; however, they are not assumed
to be extended further, because they have minimal history of legislative
extension.
The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A
Legacy for Users (SAFETEA-LU) increased the Federal tax on compressed natural
gas used in vehicles to 18.3 cents per equivalent gallon of gasoline and
provided a credit of 50 cents per gallon through September 2009. AEO2007 assumes that State and Federal taxes on compressed natural gas for vehicles
will continue at 2006 levels in nominal terms and that the tax credit will
not be extended.
The PTC for wind, geothermal, landfill gas (LFG), and some types of hydroelectric
and biomass-fueled plants, established initially by the Energy Policy Act
of 1992 [6] also is represented in AEO2007. Only new plants that come on
line before January 1, 2008, are eligible to receive the credit. AEO2007 does not assume extension of the PTC, which has been allowed to expire
in the past, even though it has typically been renewed retroactively. In
most of the extensions, the credit has been modified significantly: additional
resources have been included, resources previously eligible have been excluded,
and the structure and treatment of the credit itself have been changed.
Selected examples of Federal and State regulations incorporated in AEO2007 include the following:
- New stationary diesel regulations issued by the U.S. Environmental Protection
Agency (EPA) on July 11, 2006, which limit emissions of NOx, particulate
matter, SO2, carbon monoxide, and hydrocarbons to the same levels required
by the EPAs nonroad diesel engine regulations
- The Clean Air Interstate Rule (CAIR) and Clean Air Mercury Rule (CAMR),
promulgated by the EPA in March 2005 and published in the Federal Register as final rules in May 2005, which will limit emissions of SO2, NOx, and
mercury from power plants in the United States
- New boiler limits established by the EPA on February 26, 2004, which limit
emissions of hazardous air pollutants from industrial, commercial, and
institutional boilers and process heaters by requiring that they comply
with a Maximum Achievable Control Technology floor.
AEO2007 does not include consideration of California Assembly Bill (A.B.)
32 (discussed below), which mandates a 25-percent reduction in Californias
greenhouse gas emissions by 2020. Implementing regulations have not been
drafted and are not due to be finalized until January 2012.
In addition, Californias A.B. 1493, which establishes greenhouse gas emissions
standards for light-duty vehicles, is not considered in the AEO2007 reference
case. A.B. 1493 was signed into law in July 2002, and regulations were
released by the California Air Resources Board in August 2004 and approved
by Californias Office of Administrative Law in September 2005; however,
the automotive industry has filed suit to block their implementation, and
the Board has not yet obtained a Clean Air Act waiver from the EPA, which
is required before the regulations can be implemented.
In August 2006, seven northeastern States released a model rule for implementation
of the Regional Greenhouse Gas Initiative (RGGI) [7], as discussed below,
clarifying what had been laid out in December 2005 when the States entered
into the agreement [8]. The RGGI, which would cap greenhouse gas emissions
from power producers, requires each State to enact legislation for accomplishing
the emissions reductions. Although the State RGGI caps and timelines are
known, many aspects of their implementation remain uncertain, because the
participating States have not yet enacted the necessary legislation. Therefore,
the RGGI provisions are not modeled in the AEO2007 reference case.
AEO2007 does include the CAAA90 requirement of a phased-in reduction in
vehicle emissions of regulated pollutants. It also reflects Tier 2 Motor
Vehicle Emissions Standards and Gasoline Sulfur Control Requirements finalized
by the EPA in February 2000 under CAAA90. The Tier 2 standards for reformulated
gasoline (RFG) were required by 2004, but because they included allowances
for small refineries, they will not be fully realized for conventional
gasoline until 2008. AEO2007 also incorporates the ultra-low-sulfur diesel
fuel (ULSD) regulation finalized by the EPA in December 2000, which requires
the production of at least 80 percent ULSD (less than or equal to 15 parts
sulfur per million) highway diesel between June 2006 and June 2010 and
100 percent ULSD thereafter. It also includes the rules for nonroad diesel
issued by the EPA on May 11, 2004, regulating nonroad diesel engine emissions
and sulfur content in fuel.
More detailed information on recent and proposed legislative and regulatory
developments is provided below.
EPACT2005: Status of Provisions
EPACT2005 was signed into law by President Bush on August 8, 2005, and
became Public Law 109-058 [9]. A number of provisions from EPACT2005 were
included in the AEO2006 projections [10]. Many others were not considered
in AEO2006particularly, those that require funding appropriations or further
specification by Federal agencies or Congress before implementation.
A number of the EPACT2005 provisions not included in AEO2006 could affect
the projections. In the preparation of AEO2007 their status was reviewed,
and where possible, additional provisions were included in the projections;
however, AEO2007 still excludes those EPACT2005 provisions whose impacts
are highly uncertain or that address a level of detail beyond that modeled
in NEMS. Furthermore, EIA does not try to anticipate policy responses to
the many studies required by EPACT2005 nor predict the impacts of research
and development (R&D) funding authorizations included in the bill.
The following summary examines the status of EPACT2005 provisions that
initially could not be included in AEO2006 but potentially could be modeled
in NEMS. It focuses on provisions that are newly included in AEO2007, as
well as those that might be added in future AEOs. The discussion below
does not provide a complete summary of all the sections of EPACT2005. More
extensive summaries are available from other sources [11].
End-Use Demand Provisions
This section summarizes provisions of EPACT2005 that affect the end-use
demand sectors.
Buildings
EPACT2005 includes provisions with the potential to affect energy demand
in the residential and commercial buildings sector. Many are included in
Title I, Energy Efficiency. Others can be found in the renewable energy,
R&D, and tax titles. Most of the provisions that have been funded or for
which implementing regulations have been put in place since the publication
of AEO2006, cannot be modeled in NEMS. The status of those provisions that
could potentially be included in NEMS is summarized below.
Section 122 of Title I, Weatherization Assistance, authorizes $600 million
to weatherize low-income households. The weatherization program, in existence
since 1976, uses Federal funds to increase the energy efficiency of low-income
houses. In fiscal year (FY) 2006, funding for this program was $242 million.
FY 2007 funding proposed by the U.S. House of Representatives is set at
$250 million. The increase in funding could allow up to 3,200 more homes
to be weatherized in FY 2007 than in FY 2006. The AEO2007 reference case
includes increases in energy efficiency in existing building envelopes
to account for programs such as weatherization. At current funding levels,
roughly 100,000 homes are weatherized each year. The impact of this section
is considered in AEO2007.
Section 204 of Title II, Use of Photovoltaic Energy in Public Buildings,
authorizes funds for the establishment of a photovoltaic (PV) energy commercialization
program to procure, install, and evaluate PV solar electric systems in
public buildings. No funding has been appropriated to date for this measure.
It is not included in AEO2007.
Section 206 of Title II, Renewable Energy Security, authorizes funds
for the establishment of rebates for the purchase of renewable energy systems,
including PV, ground-source heat pumps, and solar water heaters. This program
was to be in place starting in calendar year 2006 and last through 2010;
however, no funding has been appropriated for the measure to date, and
it is not included in AEO2007.
Section 783 of Title VII, Federal Procurement of Stationary, Portable,
and Micro Fuel Cells, authorizes funds for Federal procurement of stationary,
portable, and micro fuel cells. No funding has been appropriated for the
measure to date, and it is not considered in AEO2007.
Industrial
EPACT2005 includes few provisions that would specifically affect industrial
sector energy demand. Provisions in the R&D titles that may affect industrial
energy consumption over the long term are not included in AEO2007.
Section 108 requires that federally funded projects involving cement or
concrete increase the amount of recovered mineral component (e.g., fly
ash or blast furnace slag) used in the cement. Such use of mineral components
is a standard industry practice, and increasing the amount could reduce
both the quantity of energy used for cement clinker production and the
level of process-related CO2 emissions. The proportion of mineral component
is not specified in the legislation but is to be determined by Federal
procurement rules; however, as of mid-September 2006 the rules had not
been promulgated. Section 108 also requires that the energy-saving impact
of the rules be assessed by the EPA, in cooperation with the U.S. Department
of Energy (DOE) and Department of Transportation (DOT), within 30 months
of enactment. Because regulations have not been promulgated, this section
is not considered in AEO2007. When the regulations are promulgated, their
estimated impacts could be modeled in NEMS.
Section 1321 provides for the extension of tax credits for producers of
coke or coke gas, effective for tax years beginning after December 31,
2005. Otherwise, the status of Section 1321 is unchanged. Because the bulk
of the credits will go to plants already operating or under construction,
there is likely to be little impact on coke plant capacity. Consequently,
the provision is expected to have no impact on the AEO2007 projections.
Coal Gasification Provisions
This section provides updates to the funding and implementation status
of key tax incentive provisions in Title XIII of EPACT2005 related to coal
gasification that were not addressed in AEO2006.
Section 1307 creates an investment tax credit program for qualifying advanced
clean coal projects, funded at $1.3 billion. The section also includes
an additional $350 million for qualifying gasification projects. The gasification
credit for any taxable year is equal to 20 percent of the basis of any
equipment to be used in the gasification process that is placed in service
during the year as part of a gasification project that has been certified
by DOE as eligible for the credit. The amount eligible for credit is limited
to $650 million per project. Only domestic projects that employ domestic
gasification applications are eligible. Applicants must, among other criteria,
satisfy certain financial requirements, prove that a market exists for
the projects products, and demonstrate competency in the development and
operation of the project. Credits are not allowed for gasification projects
receiving credits under the program for advanced coal projects. A certificate
of eligibility is valid for 10 fiscal years, beginning on October 1, 2005.
In February 2006, the IRS issued guidance for the Section 1307 program.
Certifications are to be issued and credits allocated to projects in annual
allocation rounds. The first round of submissions began on February 21,
2005, and closed on October 2, 2006. Overall, the period for submission
of applications is to run for 3 years, starting on February 21, 2006. As
of August 2006, 49 applications had been received, 27 of which fell under
the gasification technology program and were for CTL plants in 17 States.
The 27 projects are valued at $30 billion and request tax credits of $2.7
billion. Selection of projects to receive the credits is scheduled for
the end of November 2006.
Credits will be allocated first to projects that have CO2 capture capability,
use renewable fuel, or have project teams with experience that demonstrates
successful operation of the gasification technology. If the requested allocations
exceed $350 million, the credits will be allocated to the projects that
provide the highest ratio of synthetic gas supplied to the requested allocation
of credits. Any remaining credits will be applied to non-priority projects
that provide the highest amount of nameplate capacity. If funds remain
in the program, additional rounds will be conducted in 2007 and 2008. The
$1.3 billion in tax credits for the advanced clean coal program was accounted
for in AEO2006 in the NEMS Electricity Market Module. CTL projects are
eligible for the gasification credits, because gasification is the first
step in the CTL process; however, because the level of interest in coal
gasification projects was not known at the time, the gasification program
credits were not included in AEO2006. Given the extent of interest in the
program to date, they are included in the Petroleum Market Module for AEO2007.
Oil and Natural Gas Provisions
This section provides updates to the funding and implementation status
of key oil and natural gas provisions of EPACT2005 that were not addressed
in AEO2006. Most of the oil and natural gas provisions in EPACT2005 are
included in Title III, Oil and Gas. Others, covering R&D, are included
in Title IX.
The Federal Energy Regulatory Commission (FERC) was authorized by Section
312 to allow natural gas storage facilities to charge market-based rates
if it was believed that they would not exert market power. On June 15,
2006, FERC finalized rules implementing the provisions that would allow
an applicant for interstate natural gas storage facilities to request authority
to charge market-based rates even if a lack of market power had not been
demonstrated. The rules are intended to mitigate natural gas price volatility
by encouraging the development of new natural gas storage capacity. They
apply in circumstances where market-based rates are in the public interest
and necessary to encourage the construction of storage capacity and to
ensure that customers are adequately protected, even in circumstances where
market power may not have been demonstrated. In previous AEOs, storage
rates were allowed to vary from regulation-based rates, depending on market
conditions.
In compliance with Section 354, DOE established a competitive program to
provide grants for cost-shared projects to enhance oil and natural gas
recovery through CO2 injection, while at the same time sequestering CO2 produced from the combustion of fossil fuels in power plants and large
industrial processes. Reports issued by DOE indicate that an additional
89 billion barrels of oil could be recovered in the United States through
CO2 injection. Under the program, grants of up to $3 million will be provided
to each project selected. On September 6, 2006, DOE announced the selection
of the first project to receive one of the grants, a project sponsored
by the University of Alabama-Birmingham to implement a demonstration project
in the Citronelle oilfield in Mobile County, AL. The total project cost
is estimated at $6 million, with DOEs maximum share at just under $3 million.
Estimates indicate that an additional 64 million barrels of oil could be
recovered from the Citronelle field by this technique.
The implementation of Section 354 was not included in previous AEOs, because
NEMS does not represent project-level activities and because of the considerable
uncertainty surrounding the eventual scope of the program. For AEO2007,
however, additional oil resources have been added to account for increased
use of CO2-enhanced oil recovery technology.
Section 311 clarified the role of FERC as the final decisionmaking body
on any issues concerning onshore facilities that export, import, or process
LNG. On October 7, 2005, FERC established mandatory procedures requiring
prospective applicants for LNG terminals, related jurisdictional pipelines,
and other related natural gas facilities to begin the Commissions pre-filing
review process at least 6 months before filing an application to site and/or
construct such a facility. The procedures, which also apply to applications
for modifications of existing or authorized LNG terminals, are designed
to encourage applicants to cooperate with State and local officials.
In March 2005 and June 2006, FERC and DOE, in cooperation with DOT and
the U.S. Department of Homeland Security, conducted three public forums
on LNG designed to promote public education and encourage cooperation between
State and Federal officials in areas where LNG terminals are being considered
for construction. They were held in Boston, MA; Astoria, OR; and Los Angeles,
CA. An additional forum is planned for Houston, TX, in the 4th quarter
of 2006, fully satisfying the Section 317 requirement that a minimum of
three such forums be held. Although this provision is not explicitly represented
in the AEO2007 NEMS, the model includes an assumption that there are no
major regulatory impediments to the siting of new LNG facilities.
Section 301 authorized DOE to increase the capacity of the Strategic Petroleum
Reserve (SPR) to 1 billion barrels from its current capacity of 727 million
barrels. DOE has announced plans to add additional storage capacity to
its SPR storage sites in Big Hill, TX; Bayou Choctaw, LA; West Hackberry,
LA; and one new site in Richton, MS. DOE filed a draft site selection Environmental
Impact Statement with the EPA on May 19, 2006, for the selection of a new
site, and comments have been received. In order for the additional storage
capacity to be authorized, constructed, and ultimately filled, further
actions by Congress and the Executive Branch will be required; therefore,
it is not considered in AEO2007.
Section 369 requires DOE to initiate a process for the leasing of Federal
lands for research on oil shale, tar sands, and other unconventional fuels.
Several industry research proposals were evaluated, and on January 17,
2006, the U.S. Department of the Interiors Bureau of Land Management announced
the selection of six applicants for oil shale leases to receive further
consideration. Because the lease applications are still under consideration,
this provision is not accounted for in AEO2007.
Coal Provisions
This section provides updates to the funding and implementation status
of provisions in EPACT2005 that will affect coal supply and prices but
were not addressed in AEO2006. Many of the provisions can be found in Titles
IV and XIII of EPACT2005.
A number of coal-related provisions that were authorized by EPACT2005 but
not included in AEO2006 continue to be excluded from AEO2007. They include
four loan guarantee or cost-sharing programs. Section 411 authorized a
loan guarantee for a coal project in the Upper Great Plains, which must
employ both renewable and advanced IGCC technologies. A loan guarantee
for the Clean Coal Project in Healy, AK, authorized by Section 412, also
is excluded from AEO2007. In Section 413, EPACT2005 authorized a cost-sharing
program in support of a high-altitude (at least 4,000 feet) Western IGCC
Demonstration Project. Finally, a loan guarantee for an IGCC plant located
in a deregulated region was authorized by Section 414.
These provisions have spurred some activity and interest. For instance,
Xcel Energy, which has proposed building a facility in Colorado with 300
to 350 megawatts of generating capacity, is a potential applicant for the
Western IGCC Demonstration Project. On August 7, 2006, DOE released its
plans to form a program office with functions that include the drafting
of application guidelines for the various loan programs. It will also be
charged with the task of awarding the loan guarantees. Although NEMS has
the capability to represent these coal provisions, Congress had not appropriated
funds for the provisions as of September 1, 2006, and they are not considered
in AEO2007.
Nuclear Energy Provisions
EPACT2005 includes numerous provisions that address nuclear power generation.
This section provides
updates to the funding and implementation status of nuclear power generation
provisions in EPACT2005 that were not addressed in AEO2006.
Section 1306 of Title 13 extends the PTC of 1.8 cents per kilowatthour
(not adjusted for inflation) to any nuclear power plant with a new design
that has a construction start date before January 1, 2014, and enters commercial
operation by January 1, 2021. Under this program, the owner of the eligible
plant can reduce its tax liability by up to 1.8 cents for each kilowatthour
of plant output. For the purposes of this law, construction begins when
a utility that has applied for or been granted a combined operating license
. . . initiates the pouring of safety-related concrete for the reactor
building. The IRS published an initial set of guidelines for the program
in May 2006 and eventually will publish a set of formal rules that will
become part of the Tax Code. In EPACT2005, the per-kilowatthour tax credit
was indexed to the rate of inflation; however, the indexing provision was
eliminated in the Gulf Opportunity Zone Act of 2005 (P.L. 109-135). Consequently,
the credit would be constant in nominal dollars over time. Because the
earliest date at which the first new nuclear unit eligible for the tax
credit could become operational is about 2015, the de-indexing of the
credit has the effect of reducing its real value by about 25 to 30 percent.
There are at least three limitations on the amount of tax credits a utility
can receive. First, tax credits in any given year are limited to a maximum
of $125 per kilowatt ($125 million for a 1,000-megawatt unit). Second,
the tax credit can be applied only in the first 8 years of a plants operation.
Third, the credit is limited to a maximum of 6 gigawatts of new nuclear
capacity nationally. If the total capacity qualifying for the tax credit
exceeds 6 gigawatts, the amount of the credit per kilowatthour will be
reduced proportionally. AEO2007 assumes that up to 9 gigawatts of new capacity
will receive the Title 13 PTC at 1.2 cents per kilowatthour. (AEO2006 assumed
that 6 gigawatts would receive the full 1.8 cents per kilowatthour.) AEO2007 also assumes that participating utilities will be able to take all the
tax credits in each of the first 8 years of their qualifying units operation.
Title 17 of EPACT2005 allows the Government to guarantee loans used to construct
new energy technologies that reduce or avoid greenhouse gases, including
new nuclear power plants. The Secretary of Energy can guarantee a loan
of up to 80 percent of the projects cost; however, DOE will not guarantee
more than 80 percent of the total debt. Thus, if a utility decided to fund
a project with 80 percent debt and 20 percent equity, DOE would only guarantee
up to 64 percent of the projects total cost. Such loan guarantees would
affect the economics of nuclear power, because they would reduce the effective
interest rates on the debt and allow utilities to use much more debt financing.
The Secretary of Energy will choose the projects that will receive the
loan guarantees. The factors to be considered in the selection of projects
include:
- A relatively low probability of failure
- The extent to which the project avoids, reduces, or sequesters air pollutants
or emissions of greenhouse gases
- The extent to which the project will advance the goals of the Presidents
Advanced Energy Initiative
- The extent to which the technology is ready to be employed commercially
in the United States and can yield a commercially viable product.
Because of the lack of appropriating legislation, this program is not included
in AEO2007.
Fuel Economy Standards for New Light Trucks
In March 2006, NHTSA finalized CAFE standards requiring higher fuel economy
performance for light-duty trucks in MY 2008 through 2011 [12]. Unlike
the proposed CAFE standards discussed in AEO2006 [13], which would have
established minimum fuel economy requirements by six footprint size classes,
the final reformed CAFE standards specify a continuous mathematical function
that determines minimum fuel economy requirements by vehicle footprint,
defined as the wheelbase (the distance from the front axle to the center
of the rear axle) times the average track width (the distance between the
center lines of the tires) of the vehicle in square feet.
As shown in Figure 9, the new fuel economy standards vary by model year
(MY) and by vehicle footprint. By eliminating the categories laid out in
the proposed rule, the final rule removes the opportunity for manufacturers
to reduce fuel economy requirements by altering vehicle sizes just enough
to reach lower target levels. Instead, under a continuous function approach,
each footprint value has an assigned fuel economy target, and small changes
in vehicle footprint are not rewarded with large decreases in target values.
In addition to reforming the structure of the light truck CAFE program,
NHTSA has also increased the gross vehicle weight rating (GVWR) of light
trucks covered under CAFE. NHTSA defines light-duty trucks as trucks with
a GVWR of 10,000 pounds or less, including pickups, vans, truck-based station
wagons, and sport utility vehicles (SUVs). Current CAFE standards apply
to light-duty trucks that have a GVWR of 8,500 pounds or less.
Starting in MY 2011, light truck CAFE standards will also apply to medium-duty
passenger vehicles (MDPVs), which are defined as complete heavy-duty vehicles
less than 10,000 pounds GVWR that are designed primarily for transportation
of passengers. The definition of an MDPV does not include vehicles sold
as incomplete trucks (i.e., a truck cab on chassis); vehicles that have
a seating capacity of more than 12 persons; vehicles designed for more
than 9 persons in seating rearward of the drivers seat; or vehicles equipped
with an open cargo area (e.g., a pickup truck box or bed) of 6 feet or
more in interior length. Hence, the definition of an MDPV essentially includes
SUVs, short-bed pickup trucks, and passenger vans that are within the specified
weight and weight-rated ranges. This implies that, starting in MY 2011,
all SUVs greater than 8,500 GVWR that are currently excluded from CAFE
consideration and all passenger vans less than 10,000 pounds GVWR will be
included in determining a manufacturers light truck CAFE compliance.
To provide manufacturers adequate time to adjust their product plans to
the new provision, NHTSA is making the new definition effective beginning
in MY 2011. As a result, the change will not have an immediate impact on
MY 2008-2010 vehicles. In addition, NHTSA is permitting manufacturers to
rely on either the old or the revised definition of light trucks until
MY 2011.
NHTSA has also amended the flat floor provision to include only vehicles
that have at least three rows of seats, of which the second and third rows
can be detached or folded to create a flat cargo surface. Manufacturers
currently offering minivans with folding seats will be able to take advantage
of the new definition immediately. The new CAFE standards continue to exclude
most medium- and heavy-duty pickups and most medium- and heavy-duty cargo
vans that are used primarily for agricultural and commercial purposes.
The change in the definition of a light truck can also have an impact on
the product mix that a manufacturer will offer, because some light trucks
under the current definition could be categorized as cars under the new
definition, with a higher CAFE requirement.
The reformed CAFE standards impose a unique fuel economy standard on each
manufacturer, based on the product mix sold in a given MY. For MY 2008
through 2010, manufacturers have the option of complying with either the
new reformed CAFE standard or an unreformed CAFE standard. The unreformed
CAFE standard requires manufacturers to meet an average light truck fleet
standard of 22.5 miles per gallon in MY 2008, 23.1 miles per gallon in
MY 2009, and 23.5 miles per gallon in MY 2010. All light truck manufacturers
must adhere to the new reformed standards for MY 2011 and subsequent years.
Each manufacturer is subject to an identical fuel economy target for light
truck models with the same footprint. Moreover, the same formula is applied
to determine each manufacturers required CAFE level, using the fuel economy
targets for different footprints, the targets specific for each model,
and the production levels of each model. Individual manufacturers face
different required CAFE levels only to the extent that they produce different
volumes of vehicles by footprint.
To determine compliance with the reformed CAFE standard, each manufacturers
production-weighted average fuel economy will be calculated and compared
to the calculated reformed CAFE. If the weighted average fuel economy of
all the manufacturers models is at least equal to the manufacturers calculated
reformed CAFE, then the manufacturer will be in compliance with the reformed
CAFE standard. If its actual fleet-wide average fuel economy is greater
than its required CAFE level, the manufacturer will earn credits equal
to the difference, which can be applied to any of the three preceding or
subsequent model years. With this allowance, manufacturers will not be
penalized for occasionally failing to meet the targets (due to market conditions,
for example) but only for persistent failure to meet them. If the average
fuel economy of a manufacturers annual car or truck production falls below
the defined standard, the manufacturer will be required to pay a penalty
proportional to its total production for the U.S. domestic market.
The new CAFE standards are captured in the AEO2007 projections. For MY
2008 through 2011, manufacturers are assumed to adhere to the increases
in unreformed light truck standards. For MY 2011, the AEO2007 applies a
fleet-wide standard of 24 miles per gallon, based loosely on the change
between 2010 and 2011 in the proposed footprint-based standards. Because
no further changes in fuel economy standards beyond 2011 are assumed, the
projected increase in light truck fuel economy after 2011 reflects projected
technology adoption resulting from other market forces.
Regulation of Emissions from Stationary Diesel Engines
On July 11, 2006, the EPA issued regulations covering emissions from stationary
diesel engines [14] New Source Performance Standards that limit emissions
of NOx, particulate matter, SO2, carbon monoxide, and hydrocarbons to the
same levels required for nonroad diesel engines [15]. The regulation affects
new, modified, and reconstructed diesel engines. Beginning with MY 2007
[16], engine manufacturers must specify that new engines less than 3,000
horsepower meet the same emissions standard as nonroad diesel engines.
For engines greater than 3,000 horsepower, the standard will be fully effective
in 2011 [17]. Stationary diesel engine fuel will also be subject to the
same standard as nonroad diesel engine fuel, which reduces the sulfur content
of the fuel to 500 parts per million by mid-2007 and 15 parts per million
by mid-2010.
Stationary diesel engines are used to generate electricity, to power pumps
and compressors, and in irrigation systems. It has been estimated that
there were 663,780 such engines larger than 50 horsepower in use in 1998
[18]. The EPA estimates that 81,500 engines will be subject to the controls
by 2015 and that total pollutant reductions will be more than 68,000 tons
per year.
The new standards for stationary diesel engines are included in AEO2007,
but they are unlikely to affect the projections materially. The nonroad
diesel standards were incorporated in the AEO projections previously, beginning
with AEO2005.
Federal and State Ethanol and Biodiesel Requirements
EPACT2005 requires that the use of renewable motor fuels be increased from
the 2004 level of just over 4 billion gallons to a minimum of 7.5 billion
gallons in 2012, after which the requirement grows at a rate equal to the
growth of the gasoline pool [19]. The law does not require that every gallon
of gasoline or diesel fuel be blended with renewable fuels. Refiners are
free to use renewable fuels, such as ethanol and biodiesel, in geographic
regions and fuel formulations that make the most sense, as long as they
meet the overall standard. Conventional gasoline and diesel can be blended
with renewables without any change to the petroleum components, although
fuels used in areas with air quality problems are likely to require adjustment
to the base gasoline or diesel fuel if they are to be blended with renewables.
Before EPACT2005, a major portion of the RFG pool was blended with methyl
tertiary butyl ether (MTBE) to meet required oxygen levels, increase volume,
improve octane, and maintain compatibility with existing petroleum product
pipelines without a large increase in gasoline volatility. The oxygen content
was required under CAAA90 [20]. Ethanol is the only other economically
feasible oxygenate, but it is incompatible with existing pipelines because
of its affinity for water and causes substantial increases in gasoline
volatility. Because MTBE was easier to blend and ship, refiners preferred
to meet oxygen requirements with MTBE. Over the past several years, however,
various State and local governments have banned the use of MTBE, and some
have even brought lawsuits against MTBE producers over concerns that spilled
MTBE and gasoline containing MTBE were polluting groundwater.
In EPACT2005, Congress repealed the oxygen requirement for Federal RFG
but declined to prohibit defective product claims against producers and
blenders of MTBE. Refiners believed that the lack of an oxygenate requirement
would increase their liability in future groundwater contamination cases
and voluntarily eliminated MTBE from the gasoline pool in the summer of
2006.
Several of the largest MTBE-consuming States had already banned the use
of MTBE and switched to ethanol-blended gasoline by the time EPACT2005
was passed. California, New York, and Connecticut implemented MTBE bans
in 2004 [21]. Ethanol distillers, petroleum refiners, and petroleum product
terminal operators invested in process changes and additional tanks to
accommodate the ethanol. Despite the flexibility allowed by the EPACT2005
RFS and its repeal of the oxygen content requirement, refiners began using
ethanol in all RFG in summer 2006.
Overall levels of ethanol and biodiesel use are projected to exceed the
EPACT2005 requirement in all AEO2007 cases, given the projected prices
for corn and crude oil, the lack of viable substitutes for MTBE, and extension
of the tax credit for ethanol blending [22]. EPACT2005 requires the use
of 250 million gallons per year of ethanol produced from cellulose after
2013. Production of cellulosic ethanol rises only to the minimum requirement
in the AEO2007 reference case, because the projected capital costs of cellulosic
ethanol plants are significantly higher than those of corn ethanol plants.
An older Federal energy law has been used specifically to promote biodiesel.
The Energy Policy Act of 1992 required certain vehicle fleets to purchase
alternative-fueled light vehicles, but the vehicles were not actually required
to run on alternative fuels. The Energy Conservation Reauthorization Act
of 1998 allowed the purchase of 450 gallons of pure biodiesel to offset
the requirement to purchase one alternative-fueled light vehicle [23].
In AEO2007, biodiesel demand for Federal fleet purchase offsets is projected
to be 7.4 million gallons per year in 2012 and 8.8 million gallons per
year in 2030.
Several States have their own requirements for ethanol and biodiesel in
their motor fuel supplies, which are reflected in AEO2007. Minnesota, a
major producer of ethanol, has required all gasoline to contain at least
7.7 percent ethanol since 1997 [24]. Hawaii requires 85 percent of its
gasoline to contain 10 percent ethanol, effective on April 2, 2006 [25].
The intention of the law is to spur local production of ethanol from sugar,
but the ethanol could also come from the U.S. mainland or from Brazil.
Minnesota was also the first State to require biodiesel blending into diesel
fuel, at 2 percent by volume [26]. The requirement became effective in
mid-2005, when two new biodiesel plants, each with 30 million gallons per
year capacity, began operation in the State. The law was waived several
times because of quality problems with the biodiesel, but it is again in
effect. Washington requires 2 percent ethanol in gasoline and 2 percent
biodiesel in diesel fuel no later than November 30, 2008. The requirement
will increase to 5 percent once the State can produce biodiesel equal to
3 percent of its diesel demand [27]. Louisiana enacted a requirement for
2 percent ethanol in gasoline and 2 percent biodiesel in diesel fuel, once
sufficient capacity is built in-State [28, 29]. Assuming that Louisianas
2-percent and Washingtons 5-percent requirements are triggered, Louisiana,
Minnesota, and Washington will require 102 million gallons of biodiesel
in 2012 and 146 million gallons in 2030.
The Federal and State policies on renewable fuels have various effects
on gasoline supply and price. The substitution of ethanol for MTBE in RFG
reduces the yield of gasoline and gasoline components from a given refinery
configuration. In the long run, refiners are expected to make additional
investments to get back some of the gasoline capacity they lost.
Because ethanol currently is economically competitive as a gasoline blending
component in Minnesota, its use in that State is not dependent on the ethanol
content requirement, which is estimated to have no adverse impact on gasoline
prices. Hawaii, on the other hand, must either produce ethanol from costly
sugar or ship ethanol from the U.S. mainland or Brazil. Because both options
are expected to be expensive, it is likely that Hawaiis program will raise
gasoline prices. The biodiesel requirements in Minnesota, Louisiana, and
Washington may increase the availability of diesel fuel in the short run
and are likely to increase diesel prices after the Federal motor fuels
excise tax credits for blending biodiesel expire. In the longer run, renewable
fuels requirements do not affect the availability of gasoline and diesel
fuel, because refiners are expected to adjust refinery expansion plans
in light of these mandates.
Federal Fuels Taxes and Tax Credits
The AEO2007 reference case and alternative cases generally assume compliance
with current laws and regulations affecting the energy sector. Some provisions
of the U.S. Tax Code are scheduled to expire, or may be subject to adjustment,
before the end of the projection period. In general, scheduled expirations
and adjustments provided in legislation or regulations are assumed to occur,
unless there is significant historical evidence to support an alternative
assumption. This section examines the AEO2007 treatment of three provisions
that could have significant impacts on U.S. energy markets: the gasoline
excise tax, biofuel (ethanol and biodiesel) tax credits, and the PTC for
electricity generation from certain renewable resources.
Excise Taxes on Highway Fuels
Excise taxes on highway fuels have been a dedicated source of funding for
the Federal Highway Trust Fund since its creation in 1956. The Federal
Government levies a tax of 18.4 cents per gallon on domestic gasoline sales
and 24.4 cents per gallon on diesel fuel. The tax levels were last adjusted
in 2003. Since 1932, when the first Federal excise tax on gasoline was
imposed, it has been adjusted by Congress almost 20 times.
Because the statutes do not specify that the Federal excise taxes on highway
fuels will be adjusted for inflation, and because they have not been adjusted
at regular intervals in the past, they are assumed to remain at current
levels in nominal terms through 2030. This assumption can, however, result
in seemingly inconsistent results. For example, both the Federal Highway
Administration and the Congressional Budget Office (CBO) project that the
Highway Account in the Highway Trust Fund will have a negative balance
by 2009, based on their respective receipts and outlays [30, 31]. Because
EIA does not track expenditures on specific transportation infrastructure
requirements, the AEO2007 projections for vehicle miles traveled are not
affected by the loss of funding for upkeep of the Nations transit system,
including maintenance of highways and bridges, which would be necessary
to support the projected levels of vehicle use.
In addition to the Federal excise tax on highway fuels, the States and
some local governments also levy excise or sales taxes on highway fuels.
State and local fuel taxes are kept constant in real terms in AEO2007,
based on analysis of aggregate historical adjustments to State and local
fuel taxes, and reflecting the calculation of State sales taxes as a percentage
of the sales price of the fuel [32].
Biofuels Tax Credits
The ethanol tax credit provides a credit against Federal gasoline taxes
that is worth 51 cents for every gallon of ethanol blended into the gasoline
pool. For a typical gasoline blend with 10 percent ethanol, the credit
reduces the Federal excise tax (18.4 cents per gallon) by 5.1 cents, resulting
in an effective tax rate of 13.3 cents per gallon for the blender. Currently,
the ethanol tax credit is scheduled to expire in 2010; however, it has
been in effect since 1978, and while it has been adjusted both up and down,
it has consistently been extended [33]. AEO2007 assumes that reauthorizations
will continue throughout the projections.
Biodiesel also receives a tax credit, at $1.00 per gallon for biodiesel
produced from virgin oils and 50 cents per gallon for biodiesel produced
from recycled oils. The credit is scheduled to expire in 2008, and AEO2007 assumes that it will not be reauthorized. The biodiesel tax credit was
established by the American Jobs Creation Act of 2004, with a 2006 expiration
date. It was extended to 2008 in EPACT2005, after the industry had sought
an extension to 2010 [34]. If the credit is reauthorized after 2008, it
will have a significant impact on biodiesel production.
Production Tax Credit for Renewable Electricity Generation
A PTC of 0.95 to 1.9 cents per kilowatthour [35] is provided for sales
of electricity generated from certain renewable resources at qualifying
facilities for the first 10 years of their operation. The PTC is adjusted
by the IRS each year, based on the annual inflation rate. First established
in 1992, the PTC has been allowed to expire three times, followed by after-the-fact
reauthorizations [36]. It has been modified significantly with each extension,
including changes in the qualifying resources (adding some, removing others),
the value and duration of the credit for certain resources, and the interaction
with other aspects of the Tax Code (such as the alternative minimum tax).
While the AEO2007 reference case assumes that the PTC will expire at the
end of 2007, both AEO2007 and previous AEOs include alternative cases that
consider the impacts of a PTC extension.
Electricity Prices in Transition
The push by some States to restructure electricity markets progressed rapidly
throughout the late 1990s. Although the energy crisis in California during 2000 and 2001 slowed the momentum, 19 States and the District of Columbia
currently have some form of restructuring in place. In addition, Washington
State, which has not restructured its electricity market, allows its largest
industrial customers to choose their suppliers.
Many States put in place special regulations to protect customers during
the transition. For most, this meant a specified period of guaranteed price
stability in the form of rate cuts or rate freezes, after which the market
was expected to be sufficiently competitive to reduce the need for price
regulation. Low transitional rates in most cases were mandated by State
utility commissions and offered by regulated utilities to customers who
could not or did not choose a competitive suppliera service often referred
to as Standard Offer Service (SOS). Some States required utilities to offer
a separate service, often called Provider of Last Resort (POLR) service,
for customers who left, or were dropped by, their competitive suppliers.
POLR service sometimes offered less price protection than SOS.
The late 1990s saw a promising start to competition. The fuel prices paid
by generators were low enough for competitive electricity suppliers to
offer rates slightly lower than SOS prices. From 2000 on, however, rapidly
increasing fuel prices caused many competitive suppliers to go out of business,
because the price of wholesale electricity rose above the price at which
they had contracted to sell it.
Since 2004 many State-mandated transition periods with fixed prices have
been coming to a close, with competitive retail markets still not developed
for large groups of customers. Most residential and small commercial customers
have no offers from competitive suppliers, leading many State utility commissions
to consider the possibility of extending regulated, cost-of-service rates
for SOS customers. Most of those States are now trying to jump-start competitive
markets by having electricity suppliers bid for the right to sell energy
to SOS customers. Table 2 summarizes the changes that have been made to
SOS pricing in key regions and States since the start of restructuring.
It also shows the percentages of retail load currently being sold directly
to consumers by competitive retailers.
Most States initially required distribution utilities to offer SOS at a
discount from regulated rates throughout the transition period, while a
few States experimented with options that encouraged some competition.
Texas and Massachusetts required utilities to offer both SOS and POLR service.
The SOS provided rate stability and price reductions; the price of POLR
service was determined by competitive bid. New York offered rate cuts for
only 1 year and required most of its large SOS energy users to pay hourly
market prices. In Maine, winners of competitive bids supplied SOS loada
method that was soon adopted by Pennsylvania for its largest utility. Both
States still had mandated rate caps, however, so that in years when fuel
prices were too high for load to be served at prices below capped rates,
too few suppliers bid to provide SOS at competitive prices. Maine responded
by raising rate caps, which has allowed the auction program for SOS to
attract multiple bidders and competitive suppliers to attract more retail
customers.
In 2002, New Jersey held the first auction to supply Basic Generation Service
(its name for SOS) for the last year of its designated transition period.
The auction attracted sufficient bidders, and New Jersey has continued
to hold an annual descending clock auction to supply SOS. In a descending
clock auction the bidding starts high, and prices tick down when supply
is greater than demand. The auction ends with the price at which the amount
of supply equals demand. Other States have considered the descending clock
auction as a means of providing SOS competitively to customers who do not
have access or have not chosen retail competitive suppliers. Illinois,
which adopted the method, recently held an auction for its 2007 SOS load.
Other States have decided to jump-start competition as transition periods
end, rather than extend rate caps. In the East, Maryland (starting in 2004),
the District of Columbia and Massachusetts (since 2005), and Delaware and
New Hampshire (since 2006) have required utilities to submit requests for
proposals to serve load for SOS customers and have chosen the lowest bidding
supplier. Pennsylvania has been negotiating with more utilities to offer
SOS for competitive bid. Currently, the State has a proposed rulemaking
out for comment that seeks to require each utility at the termination of
its transition period to pass through the cost of competitively bid SOS.
In Ohio, FirstEnergy has tried to hold an auction for the supply of its
SOS obligation but has not attracted many bidders. In Texas, where SOS
customers were automatically transferred to retail affiliates at the start
of competition, utilities whose districts have at least 40 percent of their
load supplied competitively can now offer SOS if it is bid out competitively.
In addition to bidding out SOS, New York, Maryland, and New Jersey require
large commercial and industrial customers to pay hourly market prices if
they have not chosen a competitive supplier; subsequently, most large customers
in the three States have chosen competitive suppliers that offer price
hedges to decrease possible price volatility or, in the case of New York,
have bought hedging products separate from energy supply.
Each State has a slightly different requirement for the provision of SOS,
but usually the competitive proposals are to supply load for periods of
several months to 3 years, depending on the customer group or the amount
of load in each customer group. The supply decrement or tranche is chosen
on the basis of the lowest bid. Providing load in this manner is thought
to allow prices to be determined competitively, but with much less volatility
than would occur if energy were bought hourly on the open market. SOS loads
for residential and small commercial customers usually are fixed for longer
periods than are loads for customers who use larger amounts of electricity.
In AEO2007, electricity prices are projected for 13 electricity supply
regions. The weighted average of the prices constitutes the national electricity
price projection. For competitive regions, price projections are based
on marginal price calculations to simulate the pricing methods of hourly
spot markets. It is assumed that a region will take 10 years after the
implementation of competitive markets to become fully competitive, and
so the amount of competitive load increases by 10 percent each year until
100 percent of electricity load is priced by marginal energy calculations.
Until then, part of the load (as well as any other load from regulated
States) is priced using cost-of-service calculations. Reliability costs
and taxes are added to the weighted average of hourly marginal energy costs
and are passed directly to the consumer. Transition price cuts and freezes
have been factored into the AEO2007 cases, although most have been phased
out as initial transition periods have come to an end.
In regulated areas, unless a utility has an automatic fuel adjustment clause,
customers do not immediately experience increases or decreases in generating
costs, since utilities must wait until the next rate case in order to change
rates. As a result, time lags between changes in electricity costs and
changes in final prices to consumers are factored into the projections
of regulated prices.
In past AEOs it was assumed that prices in fully competitive regions would
reflect spot market prices and would be passed on to consumers immediately.
The end of price reductions and caps in many States, along with the increase
in competitively bid SOS load, is expected to push competitive regions
closer to that representation of competition; however, most customers in
fully competitive regions will not experience price changes immediately
in response to changes in market generation costs.
In the interest of balancing the growth of competitive markets with price
stability for customers, regulators in some States have mandated that SOS
contracts be based on spot market prices but fixed for some period of time.
Also, competitive supply often is offered at fixed prices for the contract
period. Consequently, for AEO2007, lags have been built into the calculation
of competitive energy prices to simulate the delay from the time suppliers
experience cost changes to the time consumers experience price changes
as a result of the length of fixed-price contracts for SOS and competitive
retail service. Markets in deregulated regions are expected to become increasingly
competitive over the long term, and it is assumed that the lag between
the time when energy suppliers pay for energy on the spot market and the
time when customer charges reflect those costs will be 6 months. For the
short term, the lag is assumed to average 1 year in some regions.
State Renewable Energy Requirements and Goals: Update Through 2006
AEO2006 provided a review of renewable energy programs that were in effect
in 23 States at the end of 2005 [37]. Since then (as of September 1, 2006),
no new State programs have been adopted; however, several States with renewable
energy programs in place have made changes as they have gained experience
and identified areas for improvement. Revisions made over the past year
range from clarification or modification of program definitions, such as
which resources qualify, to substantial increases in targets for renewable
electricity generation or capacity. The following paragraphs provide an
overview of substantive changes in the design or implementation of State
renewable energy programs.
The Arizona Corporation Commission currently is engaged in a rulemaking
process for the States energy portfolio standard (EPS), scheduled to run
through the end of 2006 [38], which could lead to substantial changes in
the Arizona program [39]. The most significant change proposed is an increase
in the States renewable electricity generation target. Pending final approval
by the Commission and the Arizona Attorney General, the EPS target would
increase from 1.25 percent of affected electricity sales to 15 percent.
The new requirement would also allow trading of renewable energy credits
among utilities to facilitate compliance. In addition, several new resources
would be qualified to meet program requirements, including new small hydroelectric
facilities (less than 10 megawatts) and geothermal power.
The original legislative authority for Californias RPS, Senate Bill (S.B.)
1078, established a target of 20 percent renewable electricity generation
by 2017. Subsequently, the California Energy Commission and California
Public Utility Commission set an administrative goal of 20 percent by 2010
and 33 percent by 2020 [40]; however, key funding mechanisms were still
tied to the legislative 2017 target [41]. On September 26, 2006, Governor
Schwarzenegger approved S.B. 107, which codifies the target of 20 percent
by 2010 and calls for a formal study of the 2020 target [42]. S.B. 107
also modifies requirements for electricity generation from other States
to qualify for the California RPS. Out-of-State generators are now limited
to 10 percent of associated supplemental energy payments (SEPs) but have
fewer restrictions on physical deliveries of power into the California
market.
Connecticut has received new statutory authority to expand the area in
which qualifying credits can be generated for the States RPS program and
to use renewable energy credits in lieu of physical energy delivery for
program compliance [43]. In addition to the New England Independent System
Operator territory, credits generated in New York, Pennsylvania, New Jersey,
Delaware, and Maryland may also be used to satisfy program requirements,
upon a finding that each State has a comparable RPS program.
With one of the oldest RPS programs, Maine has passed an additional requirement
that 10 percent of all electricity generation growth must come from renewable
resources [44]. Maines existing target, 30 percent of total generation,
had already been exceeded when the original RPS-enabling statute was enacted.
The new law presumably will require the addition of new generating resources
to meet the incremental requirement.
Changes in the Massachusetts RPS program, although more incremental than
structural, have received significant notice among the affected parties.
The changes refine the rules governing the types of biomass electricity
generation facility that can qualify for the RPS program [45]. Previous
regulations did not allow generation from retooled biomass plants those
in service before 1998 but subsequently upgraded to meet current environmental
specificationsto qualify for the RPS, except by waiver. The changes allow
that portion of the output from retooled biomass plants that is in excess
of historical generation levels to qualify. This clarification is particularly
significant given the importance of biomass electricity generation in meeting
the Massachusetts target. In 2004, the latest year for which data are available,
35 percent of the compliance target came from biomass generation [46].
Nevada has issued a number of new rules within the context of the current
statutory authority for the States EPS [47]. Perhaps most significant
is the establishment of a credit trading system to facilitate compliance
by individual utilities. Credit trading is a common feature of State RPS
policy, which allows utilities to purchase compliance credits from other
utilities that have excess renewable electricity generation, in lieu of
actually generating renewable electric power. Energy efficiency programs
can now also be used to offset a portion of Nevadas renewable energy target.
The New Jersey Board of Public Utilities adopted regulations in 2006 that
increase the States renewable electricity generation target from 6.5 percent
of sales by 2008 to 22.5 percent by 2021 [48]. The new requirement includes
17.88 percent of sales from Class I renewable resources, 2.5 percent
of sales from Class II resources, and the remainder (2.12 percent of
sales) from solar resources. Solar generation in excess of the target may
be used to meet Class I or II requirements, and excess Class I generation
may be used to meet Class II requirements. Class I facilities can use a
broad range of renewable resources, including wind, ocean, geothermal,
LFG, and approved biomass resources. Class II facilities include hydropower
facilities less than 30 megawatts and approved resource recovery facilities
(trash incinerators).
Wisconsin has passed new legislation increasing the States RPS target
from 2.2 percent of electricity sales by 2012 to 10 percent by 2015 [49].
Under the new legislation, the Wisconsin Public Service Commission is required
to provide a report by 2016 indicating whether the goal of 10 percent has
been achieved and, if not, what steps are required to achieve it.
The AEO2007 reference case includes new renewable electric power projects
that have been identified. It does not include additional renewable projects
that might be required for full compliance with some State programs, because
it is not clear whether those requirements will be enforced, in light of
provisions for granting of compliance waivers, alternative compliance mechanisms,
and other discretionary enforcement options. A case where compliance with
nondiscretionary enforcement is assumed projects that most State renewable
energy targets should be achievable, with varying impacts on regional electricity
markets.
Some regions with State targets could see substantially more renewable
electricity generation with nondiscretionary compliance than is projected
in the AEO2007 reference case. State standards in the Mid-Atlantic and
New England regions could result in approximately 350 percent and 20 percent
more renewable generation by 2030, respectively, than projected in the
reference case. Biomass is expected to predominate as the fuel of choice
in those regions, which lack exploitable geothermal resources and have
only limited low-cost wind resources. While the total increase in renewable
generation in New York is just over 10 percent by 2030, generation from
nonhydropower renewable resources is nearly double the reference case projection.
In other regions, the impact of the standards is projected to be less pronounced.
For example, Texas, the Southwest, and the Northwest have either largely
met their renewable electricity requirements with existing and planned
capacity or are projected to build sufficient renewable capacity based
on economic merits within the reference case. Aggregated nationally, State
renewable energy standards would result in approximately 30 percent more
electricity generation from nonhydropower renewables in 2030 than is projected
in the AEO2007 reference case.
Although this analysis projects that most States would meet their RPS targets
without triggering compliance safety valves (such as alternative compliance
payments), it also suggests that limitations on the funding of Californias
RPS program could cause that State not to reach its legislated targets
[50]. Under current law, California utilities may apply for SEPs from the
State to cover above-market costs of acquiring renewable energy resources.
The SEPs are funded through a dedicated surcharge on consumer utility bills.
As of September 2006, the California Energy Commission, which is responsible
for administering the SEP program, had not awarded any SEPs and had developed
a current account of around $300 million. Funding authorizations through
2011 should provide an additional $77 million per year in new funds. The
surcharge authority must be renewed by 2012.
With the expiration of the Federal PTC at the end of 2007, as assumed in
this case, and limits on supplemental funding (without which compliance
is waived), California is projected to achieve a nonhydropower renewable
electricity generation share of 12 percent by 2012. Thereafter, the States
qualifying renewable generation is projected to grow only to the extent that such power is economically competitive without the SEP. This
projection may underestimate overall compliance with the California RPS
program, however, to the extent that recently passed program modifications
facilitate increased use of resources from other States.
State Regulations on Airborne Emissions: Update Through 2006
Implementation of the Clean Air Interstate Rule and Clean Air Mercury Rule
In May 2005, the EPA published two final rules aimed at reducing emissions
from coal-fired power plants. CAIR [51] requires 28 States and the District
of Columbia to reduce emissions of SO2 and/or NOx. CAMR [52] requires the
States to reduce emissions of mercury from new and existing coal-fired
plants [53].
The two rules cap emissions at the regional and national levels; however,
each State can decide how to meet its own cap, as long as the minimum program
milestones are met. For CAIR, the States have until March 2007 to submit
implementation plans to the EPA, which then will have until September 2007
to review the plans and identify modifications, if necessary. For CAMR,
the States must present their plans by November 2007, and the EPA then
will have 6 months to accept the plans or require modifications.
Both CAIR and CAMR provide States the flexibility to participate in a regional
cap and trade program. Several States, including most of those in the Northeast,
have said as of September 2006 that they will not participate in the cap
and trade program for mercury emissions under CAMR [54], because they plan
to adopt more stringent standards. In addition, some States plan to place
mandatory restrictions on individual coal-fired plants in order to reduce
the possibility that localized areas will continue to have high levels
of mercury emissions. Those restrictions differ from the Federal plan of
enforcing only statewide caps.
Final decisions regarding the structure of State programs and participation
in the regional trading program will not be made until after November 2007.
Currently, both CAIR and CAMR are represented as regional cap and trade
programs in AEO2007. This approach will be reevaluated when the final State
programs have been submitted and reviewed by the EPA.
Regional Greenhouse Gas Initiative
The governors of the seven States participating in the RGGIConnecticut,
Delaware, Maine, New Hampshire, New Jersey, New York, and Vermonthave
committed to enact legislation individually for achieving the desired emission
reductions under the agreement. The group originally consisted of nine
States, but Massachusetts and Rhode Island have withdrawn. In Maryland,
recently adopted legislation requires the State to join the RGGI by June
2007 [55]. Pennsylvania, the District of Columbia, and several Canadian
provinces are observers to the program.
When the original RGGI agreement was signed in December 2005, each participating
State agreed to cap its greenhouse gas emissions from power production
beginning in January 2009. The States were provided CO2 allocations based
on their average emissions for the 3-year period from 2000 to 2002, with
exceptions. States that had built or were anticipating new plants between
2002 and 2009 were allowed additional allowances to reflect the level of
emissions expected in January 2009. The governors of the seven States currently
participating have already agreed to their respective allowance allotments.
For the seven northeastern States, the annual cap is approximately 121
million short tons, representing a 6.1-percent increase over their combined
CO2 emissions in 2000. After January 2009, the RGGI requires each participating
State to hold its emissions at or below its CO2 allotment. The caps remain
unchanged until the end of 2014, after which they are reduced by 2.5 percent
annually. Thus, by the end of 2018, CO2 emissions in the participating
States will be 10 percent below the levels at which the allocations were
issued.
The August 2006 model rule clarifies several provisions on how States can
achieve their emission reductions. It also provides compliance flexibility
if prices rise beyond what is anticipated, although threshold levels have
not been determined. One-quarter of potential revenue from the auction
or sale of emission credits must go to consumer benefits or strategic energy
purposes. This broad category includes energy price discounts, renewable
and low-carbon energy investments, and energy efficiency programs. Also,
CO2 emission reductions by power producers before the January 2009 start
date will be credited for use during the cap period.
Other States and provinces may participate in the RGGI through carbon offset
programs. If the price of credits remains below $7 (2005 dollars) per short
ton of CO2, power producers may account for 3.3 percent of their emissions
through offset programs in any State or province, including capture of
landfill methane and sulfur hexafluoride, afforestation, end-use efficiency
programs, and agricultural emission reductions. For each ton of CO2 avoided
or sequestered in the projects, the power producer will be provided one
emission credit for use or sale. In order for an offset program to be eligible,
it cannot be part of any other State mandate and must be attributable only
to the RGGI. If the price of CO2 credits is sustained above $7 for more
than 12 months, power producers will be able to offset up to 5 percent
of their CO2 emissions. If credit prices surpass $10 for a sustained 12-month
period, then producers will be able to offset 10 percent of their emissions
and may participate in international credit markets.
The individual States still must enact their own legislation to achieve
the RGGI milestones. State legislation will determine compliance issues,
such as credit allocations, enforcement methods, and options for exiting
the agreement. Each State will be responsible for issuing its own allowances.
Some States may choose to sell them at a certain price; others may hold
auctions. They may also be given away, or the States may use a combination
of methods.
Although the State RGGI caps and timelines are known, many aspects of their
implementation remain uncertain, because the participating States have
not yet enacted the necessary legislation. Therefore, the RGGI provisions
are not modeled in AEO2007.
California Greenhouse Gas Legislation
A.B. 32, California Global Warming Solutions Act of 2006, which was signed
into law by Governor Arnold Schwarzenegger on September 27, 2006 [56],
calls for a 25-percent reduction in CO2 emissions by 2020. The first major
controls, for the industrial sector, are scheduled to take effect in 2012.
The plan grants the California Air Resources Board lead authority for establishing
how much industry groups contribute to global warming pollution, assigning
emission targets, and setting noncompliance penalties. It sets a 2009 date
for establishing how the system will work and then allows 3 years for the
States industries to prepare for the 2012 startup of mandatory emissions
reductions [57].
It is not yet known what sources of greenhouse gas emissions will be subject
to the restrictions, although the bill states that all major sources of
CO2 will be included. The bill does not mention the transportation sector,
which is covered in separate legislation. A.B. 32 also specifies that all
emissions from the generation of power consumed within the State are expected
to be subject to the new laws. Because California imports power from neighboring
States, emissions in those States may also be affected. In addition, California
collaborates on its greenhouse gas policy with the States of Washington
and Oregon through the West Coast Governors Global Warming Initiative
[58].
A.B. 32 delegates most of the responsibility for implementation and enforcement
to the California Air Resources Board. Although the bill indicates that
the reduction program will rely on market-based compliance mechanisms,
it does not indicate the course of action that will be taken to reduce emissions. Reliance on a market-based
compliance mechanism suggests the possible use of a credit trading program.
If this is the case, issues such as credit distribution, offset allowances,
price caps, and other restrictions will be decided by January 2009.
The Air Resources Board will also coordinate enforcement issues with the
States Public Utilities Commission and Energy Resources Conservation and
Development Commission. Regulations on the monitoring of greenhouse gas
emissions must be in place by 2008, when accurate reports on emissions
from all major sources will be mandatory. Final regulations for the emissions
reduction program will be presented in January 2011 and will become operative
in January 2012. Because the program specifics have not been developed,
A.B. 32 is not modeled in AEO2007.