Assumptions to the Annual Energy Outlook 2003

Table 46.  Coal Plant Retrofit Costs
                  (2001 Dollars)

Coal Plant Size (MW)

FGD Capital Costs ($/KW)

SCR Capital Costs ($/KW)

300

267

93

500

204

82

700

168

74

Source:  CUECOST3.xls model (as updated 2/9/2000) developed for the Environmental Protection Agency by Raytheon Engineers and Constructors, Inc.  EPA Contract number 68-D7-0001.
Note:  The model was run for each individual plant assuming a 1.3 retrofit factor.