Energy Information Administration Forecast Channel.  If having trouble viewing this page, please contact the National Energy Information Center at (202) 586-8800. Return to Energy Information Administration's Homepage

 

Assumptions to the Annual Energy Outlook 2002

 

Renewable Fuels Module

 

The NEMS Renewable Fuels Module (RFM) provides natural resources supply and technology input information for forecasts of new central-station U.S. electricity generating capacity using renewable energy resources.  The RFM has five submodules representing various renewable energy sources, biomass, geothermal, landfill gas, solar, and wind; a sixth renewable, conventional hydroelectric power, is represented in the Electricity Market Module (EMM).117

Some renewables, such as landfill gas (LFG) from municipal solid waste (MSW) and other biomass materials, are fuels in the conventional sense of the word, while others, such as wind and solar radiation, are energy sources that do not involve the production or consumption of a fuel.  Renewable technologies cover the gamut of commercial market penetration, from hydroelectric power, which was an original source of electricity generation, to newer power systems using biomass, geothermal, LFG, solar, and wind energy.  In some cases, they require technological innovation to become cost effective or have inherent characteristics, such as intermittency, which make their penetration into the electricity grid dependent upon new methods for integration within utility system plans or upon low-cost energy storage.

The submodules of the RFM interact primarily with the Electricity Market Module (EMM).  Because of the high level of integration with the EMM, the final outputs (levels of consumption and market penetration over time) for renewable energy technologies are largely dependent upon the EMM.  

Projections for residential and commercial grid-connected photovoltaic systems are developed in the end-use demand modules and not in the RFM; see the Distributed Generation and Cogeneration description in the “Commercial Demand Module” section of the report.

Key Assumptions

Nonelectric Renewable Energy Uses

In addition to projections for renewable energy used in central station electricity generation, the AEO2002 contains projections of nonelectric renewable energy uses for industrial and residential wood consumption, solar residential and commercial hot water heating, blending in transportation fuels, and residential and commercial geothermal (ground-source) heat pumps. Assumptions for their projections are found in the residential, commercial, industrial, and petroleum marketing sections of this report.  Additional minor renewable energy applications occurring outside energy markets, such as direct solar thermal industrial applications or direct lighting, off-grid electricity generation, and heat from geothermal resources used directly (e.g., district heating and greenhouses) are not included in the projections.

Electric Power Generation

The RFM considers only grid-connected central station electricity generation. The RFM submodules that interact with the EMM are the central station grid-connected biomass, geothermal, landfill gas, solar (thermal and photovoltaic), and wind submodules.  Most provide specific data or estimates that characterize that resource in a useful manner.  In addition, a set of technology cost and performance values is provided directly to the EMM.  These values are central to the build and dispatch decisions of the EMM.  The values are presented in Table 38.  Overnight capital costs and other extended performance characteristics are presented in Table 69.

Conventional Hydroelectricity

The Hydroelectric Power Data File in the EMM represents reported plans for new conventional hydroelectric power capacity connected to the transmission grid and reported on Form EIA-860, Annual Electric Generator Report, and Form EIA-867, Annual Nonutility Power Producer Report.  It does not estimate pumped storage hydroelectric capacity, which is considered a storage medium for coal and nuclear power and not a renewable energy use.  However, the EMM allows new conventional hydroelectric capacity to be built in addition to reported plans.  Converting Idaho National Engineering and Environmental Laboratory information on U.S. hydroelectric potential, the EMM contains regional conventional hydroelectric supply estimates at increasing capital costs.  All the capacity is assumed available at a uniform capacity factor of 45 percent.  Data maintained for hydropower include the available capacity, capacity factors, and costs (capital, and fixed and variable operating and maintenance).  The fossil-fuel heat rate equivalents for hydropower are  provided to the report writer for energy consumption calculation purposes only. Because of hydroelectric power’s position in the merit order of generation, it is assumed that all available installed hydroelectric capacity will be used within the constraints of available water supply and general operating requirements (including environmental regulations).

Capital Costs

The capital costs of renewable energy technologies are modified to represent two phenomena:

For a description of NEMS algorithms lowering generating technologies’ capital costs as more units enter service (learning), see “Technological Optimism and Learning” in the Electricity Market Module section of this report.  A detailed description of the RFM is provided in the EIA publication, Renewable Fuels Module of the National Energy Modeling System, Model Documentation 2002, DOE/EIA-M069(2002) (Washington, DC, January 2002).

Solar Electric Submodule

Background

The Solar Electric Submodule (SOLES) currently includes both concentrating solar power (thermal) and photovoltaics, including two solar technologies:  50 megawatt central receiver (power tower) solar thermal (ST) and 5 megawatt single axis tracking-flat plate thin-film copper-indium-diselenide (CIS) photovoltaic (PV) technologies.  PV is assumed available in all thirteen EMM regions, while ST is available only in the six primarily Western regions where direct normal solar insolation is sufficient.  Capital costs for both technologies are determined by EIA using multiple sources, including 1997 technology characterizations by the Department of Energy’s Office of Energy Efficiency and Renewable Energy and the Electric Power Research Institute (EPRI).118 Most other cost and performance characteristics for ST are obtained or derived from the August 6, 1993, California Energy Commission memorandum, Technology Characterization for ER 94; and, for PV, from the Electric Power Research Institute, Technical Assessment Guide (TAG) 1993. In addition, capacity factors are obtained from information provided by the National Renewable Energy Laboratory (NREL).

Projections for residential and commercial grid-connected photovoltaic systems are developed in the end-use demand modules and not in the RFM; see the Distributed Generation and Cogeneration description in the “Commercial Demand Module” section of the report.

Assumptions

Wind-Electric Power Submodule

Background

Because of limits to windy land area, wind is considered a finite resource, so the submodule calculates  maximum available capacity by Electricity Market Module Supply Regions.  The minimum economically viable wind speed is about 13 mph, and wind speeds are categorized into three wind classes according to annual average wind speed.  The RFM tracks wind capacity (megawatts) within a region and moves to the next best wind class when one category is exhausted.  Wind resource data on the amount and quality of wind per EMM region come from a Pacific Northwest Laboratory study and a subsequent update.119   The technological performance, cost, and other wind data used in NEMS are derived  by EIA from consultation with industry experts.120 Maximum wind capacity, capacity factors,  and incentives are provided to the EMM for capacity planning and dispatch decisions.  These form the basis on which the EMM decides how much power generation capacity is available from wind energy.  The fossil-fuel heat rate equivalents for wind are used for energy consumption calculation purposes only.  

Assumptions

For AEO2002, the performance characteristics of wind turbine technology were updated to ensure consistency with current developments and reasonably expected improvements over the forecast period.  Two parameters were examined:  capacity factor and energy capture (energy per swept rotor area).  The evaluation resulted in assumed improved performance in both factors; the estimated 2020 capacity factor for Class 6 winds improved from 30 percent to 42 percent, and the estimated 2020 energy capture improved from 1381 kilowatthours per square meter per year to 1582 kilowatthours per square meter per year. There were corresponding changes in other wind classes and years.

Geothermal-Electric Power Submodule

Background

The Geothermal-Electric Submodule (GES), represents the generating capacity and output potential of 51 hydrothermal resource areas in the Western United States based on updated estimates provided in 1999 by DynCorp Corporation and subsequently adapted by EIA.121 Hot dry rock resources are not considered cost effective until after 2020 and are therefore not modeled in the GES.  Both dual flash and binary cycle technologies are represented.  The GES distributes the total capacity for each site (the high estimate) within each EMM region among four increasing cost categories, with the lowest cost category (the low estimate of available capacity) assigned the base estimated costs, the next assigned higher (double) exploration costs, the third assigned a 33 percent increase in drilling and field costs, and the highest assigned both double exploration and 33 percent increased drilling and field costs.  Drilling and field costs vary from site to site but are roughly half the total capital cost (along with plant costs) of new geothermal plants; exploration costs are a relatively minor additional component of capital costs. All quantity-cost groups in each region are assembled into increasing-cost supplies.  When a region needs new generating capacity, all remaining geothermal resources available in that region at or below an avoided cost level determined in the EMM are submitted (in three increasing cost subgroups) to compete with other technologies for selection as new generating supply. Geothermal capital costs decline with learning as for other technologies.  For estimating costs for building new plants, new dual-flash capacity – the lower cost technology - is assigned an 80 percent capacity factor, whereas binary plants are assigned an 80 percent capacity factor; both are assigned an 87 percent capacity factor for actual generation.

For AEO2002, the GES was modified and estimates of available supply were reduced.  First, to more realistically reflect each of the 51 sites’ capacity availability through 2020, the 40-year estimates included for AEO2001 were reduced, usually to about 100 megawatts for each of four cost levels for each site.  Second, annual maximum capacity builds were established for each site, reflecting industry practice of expanding development gradually.  For the reference case, each site was permitted a maximum development of 25 megawatts per year through 2015 and 50 megawatts per year thereafter; for the high renewables case, the 50 megawatt annual limit applies to all years.

Assumptions

Biomass Electric Power Submodule

Background

Biomass consumed for electricity generation is modeled in two parts in NEMS.  Capacity in the wood products and paper industries, the so-called captive capacity, is included in the industrial sector module as cogeneration.  Generation by the electricity sector is represented in the EMM, with capital and operating costs and capacity factors as shown in Table 38, as well as fuel costs, being passed to the EMM where it competes with other sources.  Fuel costs are provided in sets of regional supply schedules.  Projections for ethanol are produced by the Petroleum Market Module (PMM), with the quantities of biomass consumed for ethanol decremented from, and prices obtained from, these same supply schedules.

Assumptions

Fuel supply schedules are a composite of four fuel types; forestry materials, wood residues, agricultural residues and energy crops.  The first three are combined into a single supply schedule for each region which does not change for the full forecast period.  Energy crops data are presented in yearly schedules from 2010 to 2020 in combination with the other material types for each region.  The forestry materials component is made up of logging residues, rough rotten salvable dead wood and excess small pole trees.122 The wood residue component consists of primary mill residues, silvicultural trimmings and urban wood such as pallets, construction waste and demolition debris that are not otherwise used.123  Agricultural residues are wheat straw and corn stover only, which make up the great majority of crop residues.124  Energy crops data are for hybrid poplar, willow and switchgrass grown on crop land, pasture land, or on Conservation Reserve lands.125   The maximum amount of resources in each supply category is shown in Table 70.

Landfill-Gas-to-Electricity Submodule

Background

Landfill-gas-to-electricity capacity competes with other technologies using supply curves that are based on the amount of “high”, “low”, and “very low” methane producing landfills located in each EMM region.  An average cost-of-electricity for each type of landfill is calculated using gas collection system and electricity generator costs and characteristics developed by EPA’s “Energy Project Landfill Gas Utilization Software” (E-PLUS).126

Assumptions

High Renewables Case

The High Renewables case examines the effect on energy supply of using cost and performance assumptions for nonhydro, non-landfill gas renewable energy technologies approximating published goals of the relevant program offices of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy (DOE/EE).  For electric power sector technologies, the High Renewables assumptions are designed to correspond to year 2020 cost and performance goals in the Renewable Energy Technology Characterizations document jointly published by the DOE/EE and the Electric Power Research Institute (EPRI). 129  These assumptions, summarized in Table 69, include:

 

Decision Year

Weight

2000

1.00

2005

0.85

2010

0.70

2015

0.67

2020

0.64

 

Least cost geothermal sites in any case result from the interaction of (a) baseline cost estimates for each site, (b) cost adjustment factors, and (c) increased costs as least-cost units are taken and higher cost sites are chosen.  Therefore, in the high renewables case results, actual 2020 marginal capital costs by 2020 will not necessarily be lower than in the reference case but will instead show greater quantities of geothermal available and chosen before again attaining the higher marginal costs. In the high renewables case, geothermal capacity factors and fixed operations and maintenance costs (O&M) are unchanged from the reference case.

Because costs are assumed to decline (or increase, in the case of Solar Thermal) based on the exogenous cost trajectory of the Technology Characterizations, the normal learning function of the EMM does not apply to these capacity types.  Thus cost targets are achieved regardless of actual market penetration.

For the high renewables case, demand-side improvements are also assumed in the renewable energy technology portions of residential and commercial buildings, industrial processes, and refinery fuels modules.  Details on these assumptions can be found in the corresponding sections of this report.

 

Legislation

Energy Policy Act of 1992 (EPACT)

The RFM includes the investment tax and energy production credits established in the EPACT for the appropriate energy types.  EPACT provides a renewable electricity production tax credit (PTC) of 1.5 cents per kilowatt-hour for electricity produced by wind, applied to plants that become operational between January 1, 1994, and June 30, 1999; AEO2002 includes extension of the PTC (adjusted for inflation to 1.7 cents) through December 31, 2001, as provided in section 507 of the Tax Relief Extension Act of 1999.  The credit extends for 10 years after the date of initial operation.  EPACT also includes provisions that allow an investment tax credit of 10 percent for solar and geothermal technologies that generate electric power.  This credit is represented as a 10-percent reduction in the capital costs in the RFM.

Production Tax Credit

Because it is currently scheduled to expire on December 31, 2001, the PTC has no effects on wind or biomass capacity projections post 2001 for either the reference or the high renewables case.  However, H.R. 4, the “Securing America’s Future Energy Act of 2001” (SAFE Act), having passed the House of Representatives in early August of 2001 and currently pending in the Senate, would extend the PTC to December 31, 2006, as well as expand eligibility to facilities using open-loop biomass and landfill gas fuels.  The “Legislation and Regulations” section of the AEO2002 discusses the results of a NEMS case that extends the PTC to 2006 and also allows new biomass and landfill gas capacity to receive the tax credit.

 

Supplemental and Floor Capacity Additions

In addition to the reported generating capacity plans from the EIA-860A and EIA-860B and capacity projected through the use of the EMM and RFM, the AEO2002 also includes 7,865 megawatts additional generating capacity powered by renewable resources.  Summarized in Table 71 and detailed in Table 72, some of the capacity represents mandated new capacity required by state laws, EIA estimates for expected new capacity under state-enacted renewable portfolio standards (RPS), estimates of winning bids in California’s renewables funding program (Assembly Bill 1890), expected new capacity under known voluntary programs, such as “green marketing” efforts, and other publicly stated plans.  The additions do not include 382 megawatts of planned additional wind capacity contingent upon extension of the EPACT production tax credit beyond its current 2001 expiration; in addition, they do not include off-grid or distributed photovoltaics or hydroelectric power.

The projections also include 54.5 megawatts central station thermal-electric and 250 megawatts central station photovoltaic (PV) generating capacity (“Floors”) assumed by EIA to be installed for reasons in addition to least-cost electricity supply 2001-2020.

 

horizonal line image


Contact Us

URL: http://www.eia.doe.gov/oiaf/aeo/assumption/renewable.html


(Report#:DOE/EIA-0554(2002)
December 21, 2001
(Next Release: December 2002)

 

Report Contents

Download  Entire Report in PDF Format

Feedback

E-Mail Subscription Lists


Related Links

Annual Energy Outlook 2002

Supplemental Data to the Annual Energy Outlook 2002

Model Documentation

Forecasts Home Page