Electricity Reform Abroad and U.S. Investment

3. Electricity Reform and Privatization in Australia

Prior to the reforms of recent years, the supply of electricity in Australia was provided by vertically-integrated, publicly-owned state utilities meeting the needs of individual states and territories. 1 The electricity industry had never operated on a national basis. Interstate grid connections were weak and electricity trade had been limited between the interconnected states. 2 The state governments were responsible for operational and planning activities, and tariff structures. The National Commonwealth government's only involvement in the industry was through its principle shareholder status in the Snowy Mountains Hydro-electric Scheme in which the two states of Victoria and New South Wales also hold shares. Some regulatory controls by the Commonwealth were exercised, however--mainly through control over state borrowing limits, taxation, foreign ownership, and environmental regulations. 3

In 1995, Australia's population of 18 million was roughly one third that of the United Kingdom and half of Argentina's population. Australia's landmass totals almost three million square miles, almost double the size of Argentina and nearly thirty times the size of the United Kingdom. However, the majority of the population is concentrated in three states (New South Wales, Victoria, and Queensland) located in the eastern portion of the country ( Table 14 ). Consequently, these three states account for most of Australia's electricity industry. Per capita electricity consumption in Australia is roughly ten times that of Argentina and more than twice that of the United Kingdom. In 1995, Australia's electricity generation was 160 million kilowatts per hour ( Table 15 ). Australia's two most populous states New South Wales and Victoria accounted for 35 percent and 23 percent, respectively, of total domestic electricity consumption ( Table 14 and Table 15 ). 4 Electricity generation was provided primarily through coal-fired power stations, which represented about 80 percent of the total fuel usage. The remaining 20 percent of electricity generation is fueled through a combination of natural gas and hydroelectricity. Nuclear power plants have never been used for electricity generation. 5

Unlike the situation in the United Kingdom (UK), electricity reform and privatization in Australia have occurred at both the state and national levels. Although the Australian and U.S. electricity industries are in many ways very different, Australia's dual path to electricity reform bears some similarities to current developments in U.S. electricity markets. One result of Australia's dual state/national approach to electricity reform is that each state has pursued different reforms with reform efforts at the national level providing more guidance than direction. Reform at the state level differs from UK reform, which was entirely a central government effort. These distinctions are noted below. Victoria has pursued the most aggressive electricity reform measures in Australia and has most closely followed the UK model, while other states have pursued various degrees of more limited reform.

At the national level, Australia's electricity reform also differs significantly from the UK model in the operation of the national electricity pool, in the authority of the national electricity regulator, and the level of regional control. In other ways, national reforms have been quite similar to those of the United Kingdom. Australian governments have generally split up their electrical industries along functional lines, with the state of Victoria adopting the UK model's separation of electricity into four segments. A national grid and national pool are currently operating and are expected to be further developed. The new national regulatory regime is to be "light handed" and a form of price regulation (intended to promote efficiency) will be applied to the regulated sectors.

The privatization of energy is a recent, but internationally widespread, trend which has placed greater reliance on market forces and less dependence on government in the allocation of resources. Australia's electricity industry is part of this trend as state government involvement in and ownership of this industry has moved toward corporatization and privatization since 1995. The "over-capitalized investments" 6 made by the state governments in the electricity sector (generation capacity, transmission systems, and distribution) had resulted in "high levels of reserve plant margins combined with high debt levels with minimum returns." 7 Monetary restraints and debt placed pressures on the federal and state governments to reduce expenditures and increase efficiency while still providing service for the public. 8

The objective of reform in Australia was to "deliver more efficient and sustainable use of capital infrastructure and energy resources and to improve Australia's domestic and international economic performance." 9 To achieve these objectives, the government considered competition the most effective tool. In addition, the state governments estimated that electricity reform would add an estimated $5.0 billion annually 10 to the Australian Gross Domestic Product. 11

The electricity reform effort has been underway since 1991, when the various state and territorial governments agreed to work cooperatively to introduce a competitive electricity market in the southern and eastern regions of Australia. (For a general description of the structure of the Australian government, see the box entitled "The Australian Governmental System.")

At a special conference in November of 1990, the Industry Commission (a federal statutory body whose main objective was to improve the efficiency of the Australian economy) was appointed by the Commonwealth to review the electricity industry and discuss the feasibility of a national electricity grid. The Industry Commission recommended reforms that would eventually lead to the privatization of the electricity market. These reforms included: unbundling the electricity industry into separate generation, transmission, distribution sectors; privatizing and corporatizing the separate (but still state-owned) electricity transmission and distribution sectors; introducing competition into the generation sector; combining the state-owned transmission units into a single national grid; and restricting transmission and distribution businesses to the transport of electricity. In addition, the Industry Commission recommended that after privatization, tariffs should be reflective of actual costs, and cross-subsidies (from urban to rural consumers) should be eliminated. 12 Six months later, the Commonwealth, state and territorial heads of government established the National Grid Management Council as an intergovernmental advisory body to develop the National Electricity Code in consultation with industry, stake-holders, and the public. 13

In October 1994, the National Grid Management Council prepared the first draft of the national electricity market report entitled "Restructuring of the Electricity Supply Industry in Australia." This report addressed the broad objectives for the proposed national electricity market, as well as the different types of trading arrangements to be provided, how it would operate, and how its security would be maintained. The report's recommendations were endorsed by each of the state governments and the Australian Capital Territory. In September 1995, the National Grid Management Council prepared a second report that outlined the market functions of the proposed national electricity market. The National Electricity Code (the Code) establishes the rules and procedures for operating in the competitive national electricity market. The Code was completed in September 1996 and was sent to the Australian Competition and Consumer Commission for approval in November 1996. 14

A further impetus to reform was the release of the 1993 National Competition Policy Review, known as the Hilmer Commission Report. The report identified industries where reform could yield substantial benefits to Australia's economy. Electricity was one of these industries. In April 1995, the Council of Australian Governments agreed to a national competition policy reform, the National Competition Reform Act of 1995, which provides for uniform protection of consumer and business rights and increased competition in all jurisdictions. This policy would also enhance the national economic interest by improving Australia's international competitiveness, as well as encourage competition in the trading activities of government-owned enterprises.

As part of the reform package, the Commonwealth agreed to provide financial assistance payments to the states and territories totaling $4.2 billion Australian dollars 15 in return for the states meeting their agreed obligations, including the reform of their electricity, gas, water, and road transport industries. 16

Creation of the National Electricity Market

As specified, the objectives of the competitive national electricity market are:

The Australian national electricity market (NEM) is to develop in stages until a fully competitive market for electrical generation and retail supply is achieved by 2001. Although it is referred to as a national market, NEM will initially include the states of Victoria, New South Wales, South Australia, Queensland, and the Australian Capital Territory, with the possibility of an expansion into Tasmania following its grid interconnection. Western Australia and the Northern Territory will not participate in the market due to geographical and cost factors. Victoria, New South Wales, and the Australian Capital Territory are currently operating in a transitional phase of the national electricity market (NEM1). South Australia will enter the market in 1998 and Queensland is scheduled to connect to the national grid by 2001. (See the box entitled "The National Electricity Market (NEM) Time Table.")

The first phase of the NEM was scheduled for 1995 (covering New South Wales, Victoria, and the Australian Capital Territory), but the actual startup of phase 1 began on May 5, 1997. A national electricity generation pool was introduced when Victoria and New South Wales began an interstate wholesale electricity trading market, with the Australian Capital Territory participating in the linked market through New South Wales. In this market, the states still operate under a separate wholesale power pool but generators compete directly with each other (see the section entitled "National Australian Power Pool" for a discussion on the operation and structure of the new national power pool). When less expensive electricity is available in one state (e.g., Victoria), the pool allows another state (e.g., New South Wales) to import this cheaper electricity. The new power pool is intended to create a national electricity market in Australia.

Transitional Phase: Interstate Connections

Before the national electricity market can become fully operational in the southern and eastern regions of Australia, three main transmission links need to be built to interconnect these regions to form a national electricity grid. 18 Currently, the states of New South Wales, Victoria, South Australia, and the Australian Capital Territory (ACT) are connected to form a grid network. However, each government grid is not directly connected to the other state grids; instead, they are all linked together via Victoria. The grids of Victoria and New South Wales are linked with a maximum transfer capability of 1,100 megawatts (with the largest capacity transmission net-work running through the Snowy Mountains Hydro-electric Scheme). Victoria and South Australia are linked with a total transfer capability of 500 megawatts. 19 The ACT does not generate electricity; it imports its electricity from New South Wales. In 1995, interstate flows of electricity represented on average less than 2 percent of total electricity consumed within the states mentioned above (excluding ACT).

The three main links that must be built to interconnect the southern and eastern regions of Australia to form a national grid are (1) New South Wales and South Australia, (2) New South Wales and Queensland, and (3) a sub-sea link between Victoria and Tasmania with a 300-megawatt interconnection after the year 2000. In 1993, a feasibility study to evaluate the economic and environmental implications of the Victoria to Tasmania sub-sea link was both initiated and completed. In 1996, similar feasibility studies were initiated for the other two necessary grid links. In 1997, New South Wales and Queensland announced their intentions to build the actual link interconnecting their two states by 2001. 20 As of early 1997, the remaining feasibility study was still in progress. 21

The introduction of a national electricity market will change the structure, operation, and regulations of the traditional Australian electricity industry. The expected changes include: