Electricity Supply and Demand Fact
Sheet
The U.S. electric power industry is in transition as it moves toward a
competitive environment in the wholesale and retail markets. Competitive markets are expected to
encourage investments in new electric generating capacity to meet growing customer needs. These
evolving markets are also expected to ensure that sufficient future capacity will exceed the
projected peak demand. The extra capacity is needed to act as a buffer against unexpected
increases in customer demands and losses of generating supply due to events like equipment
outages, which might cause electricity blackouts.
-
The electric power industry has not determined what percentage level is
adequate for the electric generating capacity margins to guarantee electricity at all times and
under varying conditions. The capacity margins can be affected by the availability of
electricity supply (equipment failure) and by unanticipated electricity usage by customers.
Extreme weather conditions can cause both of these to happen at once, without substantial
warning. The effects of these potential supply shortages can be mitigated with larger capacity
margins, but it is difficult to determine the level of capacity margins capable of providing
adequacy at all times and under varying conditions.
-
Under the traditional regulated regime, capacity margin calculations were
considered as part of long-term planning to ensure that enough capacity was available under
typical adverse events. In the aftermath of deregulation, investor-owned utilities have
divested their generating assets. They are no longer responsible for capacity planning as in
the past. Capacity additions, therefore, may or may not keep pace with the growth in
demand.
-
Between 1978 and 1992, America's utilities' capacity margins averaged
between 25 and 30 percent. Since 1992, the capacity margins have declined to less than 15
percent nationwide. However, in 2001, the decline is expected to reverse, as capacity margins
reach 15.6 percent nationwide, with planned capacity expected to grow by 27.1 gigawatts and
demand by 15.8 gigawatts.
-
While the Nation overall has a 15.6 percent capacity margin for 2001, the
3 independent power grids that comprise the electrical systems in the lower-48 States differ in
their level of capacity margins. The largest power grid (Eastern) dominates with nearly 75
percent of total U.S. electricity demand. However, with a capacity margin of 13.9 percent, the
Eastern Power Grid has the lowest planned extra supply available this summer to meet expected
demand (see table).
-
The national capacity margin is expected to reach 18.4 percent in 2004
with electric generating capacity expected to reach 870.0 gigawatts, while electricity demand
is projected to reach 709.6 gigawatts (see graph).
|
U.S. Capacity Margins, 2001
|
|
Eastern Grid
|
Texas Grid
|
Western Grid
|
U.S. Total
|
Demand
(Megawatts)
|
501,405
|
53,414
|
114,830
|
669,649
|
Supply
(Megawatts)
|
582,223
|
69,769
|
141,068
|
793,060
|
Capacity Margins
(Percent)
|
13.9
|
23.4
|
18.6
|
15.6
|
Related
Websites
|