Home > Electricity > Electricity Publications > Electric Power Annual 2000 Volume II > HTML Data Tables > Table 37
 Date of Data: 2000
 Report Released: November 2002
 Next Release Date: January 2003

Table 37. Net Internal Demand, Planned Capacity Resources, and Capacity Margins by North American Electric Reliability Council Region and Hawaii, 2001 Through 2005
(Megawatts)

epav2t37.txt (page 3 of 4)  (Next Page)  (Previous Page)  (First Page)  (Last Page) 
North American Electric Reliability Council Region and Hawaii 2001 2002
Net Internal Demand Planned Capacity Resources Capacity Margin (percent) Net Internal Demand Planned Capacity Resources Capacity Margin (percent)
 
Winter
ECAR 87,190 119,870 27.3 88,904 118,958 25.3
ERCOT 41,606 72,597 42.7 44,868 80,751 44.4
FRCC 38,199 45,665 16.3 39,492 48,425 18.4
MAAC 43,110 64,854 33.5 43,763 73,261 40.3
MAIN 41,250 63,075 34.6 41,470 67,853 38.9
MAPP(U.S) 23,748 32,777 27.5 24,145 33,475 27.9
NPCC(U.S) 45,650 68,173 33.0 46,388 71,790 35.4
SERC 131,779 169,850 22.4 133,714 174,815 23.5
SPP 28,761 45,501 36.8 28,942 45,494 36.4
WSCC(U.S) 101,270 144,185 29.8 103,401 155,918 33.7
ContiguousU.S. 582,563 826,547 30.4 595,087 870,740 32.4
ASCC (1) (1) (1) (1) (1) (1)
Hawaii (2) (2) (2) (2) (2) (2)
U.S.Total 582,563 826,547 30.4 595,087 870,740 32.4
epav2t37.txt (page 3 of 4)  (Next Page)  (Previous Page)  (First Page)  (Last Page) 

(1) Data for ASCC (Alaska) were not filed. (2) Data for Hawaii are not submitted on this form.
       Notes: łData are projected and updated annually.  łIn 1998 several utilities realigned from SPP to SERC.  łTotals may not equal sum of components because of independent rounding.  łRepresents an hour of a day during the associated peak period. łThe summer peak period begins on June 1 and extends through September 30.  łThe winter peak period begins on December 1 and extends through March 31 of the following year.  For example, winter 2000 begins December 1, 2000, and extends through March 31, 2001.  Thus, the winter referred to here would be the winter of 2000/2001.
       Source: Form EIA-411, "Coordinated Bulk Power Supply Program".


Contact:
   Roger Sacquety
   (202)287-1745
   Internet E-Mail: roger.sacquety@eia.doe.gov