6. Quantitative Impacts of Electric Power Industry Restructuring on Fuel
Markets
This chapter presents a quantitative analysis of the likely impacts that
competitive electricity generation markets could have on fuel supply
industries. The primary tool used for the analysis is the National Energy
Modeling System (NEMS), a comprehensive model of energy markets that projects
energy supply, demand, and prices. NEMS is an integrated model that
represents the supply, conversion, and end-use demand sectors in domestic
energy markets. By balancing energy supply and demand, NEMS projects
production, imports, consumption, and prices of energy in the mid-term
forecast horizon (in this analysis, through 2015). Because restructuring
affects all energy consumers and producers, all the demand and supply modules
within NEMS were used in the analysis.
Case Descriptions and Assumptions
In order to explore the potential impacts of a competitive electricity market
on fuel markets, several cases were constructed. The regulatory, legislative,
and environmental policies that will eventually emerge are currently being
debated in a number of different forums. Therefore, there is considerable
uncertainty about the conditions under which a competitive electricity market
will operate. In order to capture this uncertainty, a range of possible
outcomes was prepared, each based on different assumptions about key
electricity and energy variables. Although these cases are not forecasts,
they do represent potential outcomes that could occur under the range of
assumptions analyzed. Two full competition cases in addition to a partial
competition case (the AEO98 reference case) are compared with a no
competition case in order to illustrate possible impacts of competition.
The first case (no competition) represents a market in which there are no
further competitive initiatives and in which participants assume that no
further move toward competition will occur. This case was developed to
provide a base against which the competition cases and the AEO98
reference case could be compared. While the AEO98 reference case
assumes that only three regions (California, New England, and New York) will
move to full competition over the next decade, it also assumes that
electricity market participants will anticipate the onset of full
competition.202 To develop the no
competition case, EIA modified the following assumptions from the
AEO98 reference case:
-
Heat rates for new plants are assumed to improve less over the forecast
horizon than in the AEO98 reference case, because there would be
less incentive for vendors to improve them if electricity markets remained
regulated. For example, while heat rates for new advanced combined-cycle
plants were assumed to be 6,350 British thermal units (Btu) per
kilowatthour in the AEO98 reference case, the no competition case
assumes that they would be only 6,668 Btu per kilowatthour by 2015, an
efficiency that is 5 percent lower (Table 18).
-
The capital costs of new generating plants are assumed to be 15 percent
higher than those assumed in the AEO98 reference case. In
regulated electricity markets with full cost passthrough, plant equipment
manufacturers are assumed to be less aggressive in lowering costs to
maintain market share. In addition, it is assumed that equipment would be
tailored to meet individual customer needs, thus reducing cost savings that
could be realized if more factory construction and modular design were
employed.
-
Capital costs for new construction are assumed to be based on the regulated
utility cost of capital, rather than on the project cost of capital used in
the AEO98 reference case. In a regulated environment, utilities
are allowed to recover their capital costs over 30 years. The
AEO98 reference case assumes higher costs of capital based on
project financing by unregulated investors. In a competitive market, new
capacity additions are riskier and investors are assumed to plan for a
20-year recovery for capital costs.
-
Both general and administrative costs, as well as operation and maintenance
costs, are assumed to decline by 5 percent, compared with the 25-percent
decline assumed for the AEO98 reference case. Much of the
incentive to cut staff and reduce costs comes from the anticipation of
competitive electricity markets. In a regulated market, these costs are
paid by consumers, dampening the incentive to reduce them.
Table 18. Comparison of Selected NEMS Assumptions
| Capacity
|
Nuclear retirement |
Same as AEO98 reference case |
Retire 24 nuclear plants prior to end of operating
license |
Retire 6 nuclear units that have announced
early retirement dates |
Same as AEO98 reference case |
| Fossil retirement |
Same as AEO98 reference case |
Retire fossil plants with operating costs > 4
cents per kWh |
Same as AEO98 reference case |
Retire fossil plants with operating costs >
6 cents per kWh |
| Upper bound on new plants |
Same as AEO98 reference case |
Up to 3 percent above optimal reserve margin
in competitive regions; 1% elsewhere |
Up to 10 percent above optimal reserve margins
in all regions |
Up to 10 percent above optimal reserve margins
|
| Renewable portfolio standard (RPS) |
None |
None |
2 percent RPS by 2000 increasing to 4 percent
by 2010 |
None |
| Electricity Demands
|
End use sector growth |
Same as AEO98 reference case |
1996-2015
| Residential |
1.6% |
| Commercial |
1.3% |
| Industrial |
1.5% |
| Total |
1.5% |
|
Same as AEO98 Reference |
1996-2015
| Residential |
2.0% |
| Commercial |
1.8% |
| Industrial |
1.6% |
| Total |
1.9% |
|
| Competitive Electricity
Prices |
Regions |
None |
New York, New England, California (phased in
by 2005) |
All regions (phased in by 2005) |
All regions (phased in by 2005) |
| Electricity Trade
|
Regions |
Same as AEO98 reference case |
Adjoining regions that have traded historically
|
Allow trading between all regional pairs with
connecting transmission capability |
Allow trading between all regional pairs with
connecting transmission capability |
| Fuel Supply
|
Oil and gas drilling costs |
Same as AEO98 reference case |
1.3 percent annual reduction in onshore drilling
costs |
Same as AEO98 reference case |
1.6 percent annual reduction in onshore drilling
costs |
| Coal productivity |
Same as AEO98 reference case |
2 percent average annual increase in productivity
|
2.5 percent average annual increase in productivity
|
2.5 percent average annual increase in productivity
|
| New Generating
Plants |
Heat rates |
5 percent higher than the AEO98 reference
case |
Based on analysis of reports and discussions
with industry, government, and the National Laboratories |
Same as AEO98 reference case |
Same as AEO98 reference case |
| Capital costs |
15 percent higher than the AEO98 reference
case |
Based on analysis of reports and discussions
with various sources from industry, government, and the National Laboratories
|
Same as AEO98 reference case |
Same as AEO98 reference case |
| Capital recovery |
30 years |
20 years |
Same as AEO98 reference case |
Same as AEO98 reference case |
| Generating Plant Costs
|
General & administrative and operation &
maintenance costs |
Decline by 5 percent from historical levels
by 2005 |
Decline by 25 percent from historical levels
by 2005 |
Same as AEO98 reference case |
Same as AEO98 reference case |
| Source: Energy Information Administration,
Office of Integrated Analysis and Forecasting, National Energy Modeling
System runs nocomp.d010698a, aeo98b.d100197a, complo3.d031298b, and
comphiD3.d031398b. |
The competition cases described below contain varying assumptions on how a
deregulated electricity market may evolve. Two full competition cases are
considered, combining assumptions about low fossil fuel use with the
AEO98 reference case electricity demand and about high fossil fuel
use coupled with higher electricity demand. While both cases assume full
competition, they differ from each other in assumptions about consumer
responses to prices, technological progress for oil and natural gas
production, legislation promoting generation from renewable sources, and
retirement decisions for fossil and nuclear generators. These competition
cases are designed to characterize the effects of competition that is more
intense than is assumed in the AEO98 reference case. While the cases
may overstate the intensity of competition, they provide an outer boundary on
the effects on electricity markets. Assumptions common to all the cases are
as follows:
-
Both the reference case and the competition cases assume that California,
New York, and New England will become fully competitive within the next
decade. Electricity prices for commercial and industrial customers in
California are assumed to remain at 1996 levels between 1998 and 2001, with
residential customers receiving a 10-percent reduction from 1996 prices
during the same period. After a transition period between 2002 and 2007,
California markets are assumed to be fully competitive by 2008. This
transition period reflects the time needed to establish the institutions
for a competitive market and to allow for recovery of stranded costs to the
extent permitted by the State. New York and New England have a similar
transition period between 1998 and 2007. In the competition cases (unlike
the AEO98 reference case), all other regions are assumed to move
to competitive markets beginning in 1998 with the same transition period
and to become fully competitive beginning in 2008. Full competition, in
addition to the cost and efficiency gains assumed, means that electricity
prices will be driven by competition among electricity generators rather
than by regulatory proceedings.203
-
Limits on power transmission are relaxed in three regions from those
assumed in the AEO98 reference case. For the competition cases, it
is assumed that Texas, New York, and New England can transmit more power to
adjacent regions than they could in the AEO98 reference case.
Texas is assumed to have an incentive to build new transmission connections
to neighboring States in order to allow its low-cost fossil plants to sell
electricity outside the State. In New York and New England it is assumed
that new transmission connections to Canada will be built, allowing
additional sales of electricity from Canada to the United States.
-
Investments in new generating capacity are assumed to exceed the levels
that would be expected on the basis of optimal economic efficiency alone.
This could occur if suppliers invest in new capacity in order to increase
their market share. The level of overbuilding to reflect this investment
behavior is assumed to be 10 percent above that which would occur under
assumptions of economic efficiency.
-
Because of competitive pressures to maintain market share, a higher rate of
improvement in coal mining productivity is assumed in the competition
cases2.5 percent annually compared with 2 percent in the
AEO98 reference case.
In order to represent outcomes from restructuring that result in higher or
lower fossil fuel consumption, additional assumptions were made in the
competition cases. The following assumptions were made for the high fossil
case:
-
Optimistic technological progress rates that lower costs for oil and
natural gas supply are assumed because of competition. Compared with the
1.3-percent annual reduction in the AEO98 reference case,
technological improvements are assumed to reduce onshore drilling costs by
1.6 percent per year. The impact of technology on costs is offset by other
factors, including rig availability and drilling levels. Improvements in
technology are assumed to result from pressure exerted by electricity
markets on oil and gas producers to lower their costs to maintain (or to
increase) their market shares.
-
Retirements of existing fossil-fueled power plants are reduced to address
the uncertainty in the price of generation services in competitive markets.
It is assumed that existing fossil-fueled power plants will be retired if
their operating costs are greater than 6 cents per kilowatthour. In the
other cases, plants with current operating costs greater than 4 cents per
kilowatthour are assumed to be retired early because they would not be
competitive given the costs and performance of new generating sources. The
higher cost criterion used in this analysis allows more fossil plants to be
available over the projection period. This assumption reflects the
uncertainty about market prices for generation services in a competitive
market as well as the value of having higher cost capacity available to
provide ancillary services such as voltage stability and reactive
power.
-
Based on estimates of elasticities observed in regulated market, a higher
level of electricity demand is assumed to capture the uncertainty of
predicting the effects that lower electricity prices would have on
consumption. In addition, the potential reduction in regulatory oversight
could cause demand-side management programs to be deemphasized, resulting
in an increase in electricity demand above what it would be if such
programs were in effect. New pricing structures, such as time-of-day
pricing, could also increase demand. The growth rate for electricity sales
(1.9 percent) is assumed to be close to the growth rate for the gross
domestic product (GDP), which averages 2.1 percent per year from 1996
through 2015. In the AEO98 reference case, electricity consumption
is projected to grow by 1.5 percent per year. In the high fossil case,
residential and commercial sector consumption of electricity was adjusted
to mirror GDP growth.
In the low fossil case, the additional assumptions include the following:
-
The low fossil case assumes that legislation mandating a renewable
portfolio standard (RPS) will be enacted. The standard is based on H.R.
655, Electric Consumers' Power to Choose Act of 1997 (Title I Section
113) submitted by Congressman Dan Schaefer (R-CO). This bill requires that
2 percent of new generation be produced from renewable sources by 2000,
increasing to 3 percent by 2005 and 4 percent by 2010. The RPS results in
higher levels of generation from renewable sources than projected in the
AEO98 reference case. Higher generation from renewable sources
dampens the demand for fossil fuels for a given level of electricity
demand. (In March 1998, the Department of Energy announced the
Administration's Comprehensive Electricity Competition Plan, which
recommends an RPS calling for 5.5 percent of generation from renewable
sources by 2010. This is about 20 billion kilowatthours more than is
assumed in the low fossil case.)
-
This case also assumes no additional retirements of nuclear capacity before
their operating licenses expire beyond those already announced. It is
assumed that uncertainty about the price of generation services in a
competitive market will encourage utilities to postpone the decision to
retire plants early. In the AEO98 reference case, about 18
gigawatts are retired 2 to 10 years before the plant licenses expire, based
on the expected need to invest additional capital to refurbish major
systems. In this analysis it is assumed that only Big Rock (1997), Haddam
Neck (1997), Maine Yankee (1997), Browns Ferry (1997), and Zion 1 &
2 (2004),204 for which retirements
already have been announced, will be retired early.
There are likely to be many innovative approaches to providing electricity
services that develop under competition. For example, power from
environmentally benign sources (i.e., green power) is currently offered in
California. Because the quantitative impacts of these programs and others
that improve the efficiency of delivering electricity services are not well
understood at this time, they were not considered in the low fossil case.
Results
Electricity Capacity and Generation
|
Figure 24. Differences in Capacity Additions from the No
Competition Case
(Click graph to view full size)
|
Decisions about capacity additions are based on assumptions about capital
investments, cost of capital, the economic life of the plant, operating
efficiency, and fuel expenditures that determine costs over the life of the
plant. Using those criteria as a basis for decisions results in
natural-gas-fired turbines and combined-cycle plants garnering most of the
market for new generation in all the cases analyzed. This outcome is driven by
the high efficiency of gas-fired turbines and the expectation that natural gas
prices will grow moderately over the next 20 years. Gas-turbine technologies
are also attractive over the next several years because they are competitive
during shoulder and peak periods of electricity demand. These are the periods
for which most of the new capacity will be needed.
Currently there is more than sufficient baseload capacity to meet electricity
demand, and new baseload capacity will not be needed in significant
quantities for several years. From 1996 to 2015, additions of coal-fired
capacity range from about 20 to 49 gigawatts for all the cases analyzed. In
contrast, additions of natural-gas-fired turbine and
combined-cycle capacity range from about 256 to 324 gigawatts; however,
the impact of new natural-gas-fired turbines (132 to 158 gigawatts) is less
than the level of capacity additions would indicate because, unlike
coal-fired plants, these units operate at low capacity factors.
Even with the dominance of gas-fired capacity additions in mind, there are
variations in capacity choice among the cases of this study (Figure 24).
|
Figure 25. Electricity Generation by Fuel Type, 1997, 2005,
2015
(Click graph to view full size)
|
For example, coal-fired capacity additions in the no competition case are
higher by 2.7 gigawatts than those in the AEO98 reference case by 2005
(Table 19) because capital investment costs are assumed to be recovered over 30
years instead of 20 years. This assumption improves the economics of more
capital-intensive projects, such as coal-fired plants, compared with less
capital-intensive projects, such as natural-gas-fired turbines and
combined-cycle plants. The higher level of coal capacity additions lowers
gas-fired capacity additions by about 10 gigawatts, most of which is turbines.
This trend continues through 2015, when there are about 14 gigawatts more of
coal capacity additions than in the AEO98 reference case. The higher
coal capacity offsets gas-fired capacity, which is more than 19 gigawatts
lower. By 2015, most gas capacity additions are combined-cycle units. The
generation from coal- and natural-gas-fired capacity follows similar patterns
(Table 20). Coal-fired generation in 2015 is 4 percent more than in the
AEO98 reference case, and gas-fired generation is almost 12 percent
lower (Figure 25).
Table 19. Electricity Generating Capability (Thousand
Megawatts)
| Electricity Generators
|
| Capability |
| Coal Steam |
305.3 |
304.8 |
302.1 |
299.3 |
304.8 |
330.3 |
316.0 |
300.7 |
325.0 |
| Other Fossil Steam |
138.1 |
103.6 |
103.6 |
103.6 |
116.3 |
97.1 |
97.1 |
97.1 |
109.8 |
| Combined Cycle |
15.3 |
69.2 |
71.3 |
68.7 |
76.7 |
139.0 |
154.9 |
150.3 |
182.4 |
| Combustion Turbine/Diesel |
76.7 |
168.2 |
176.2 |
184.4 |
182.2 |
206.8 |
210.1 |
218.7 |
232.3 |
| Nuclear Power |
100.8 |
86.8 |
86.8 |
96.1 |
86.8 |
63.9 |
63.9 |
70.7 |
63.9 |
| Pumped Storage |
19.9 |
19.9 |
19.9 |
19.9 |
19.9 |
19.9 |
19.9 |
19.9 |
19.9 |
| Fuel Cells |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Renewable Sources |
88.6 |
92.2 |
92.9 |
108.3 |
92.7 |
93.5 |
94.7 |
117.9 |
95.4 |
| Total |
744.7 |
844.7 |
852.7 |
880.3 |
879.3 |
950.5 |
956.7 |
975.3 |
1,028.7 |
| Cumulative Planned Additions |
| Coal Steam |
2.4 |
3.2 |
3.2 |
3.2 |
3.2 |
4.7 |
4.7 |
4.7 |
4.7 |
| Other Fossil Steam |
0.0 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
| Combined Cycle |
2.0 |
2.7 |
2.7 |
2.7 |
2.7 |
3.0 |
3.0 |
3.0 |
3.0 |
| Combustion Turbine/Diesel
|
3.8 |
5.2 |
5.2 |
5.2 |
5.2 |
5.2 |
5.2 |
5.2 |
5.2 |
| Nuclear Power |
1.2 |
1.2 |
1.2 |
1.2 |
1.2 |
1.2 |
1.2 |
1.2 |
1.2 |
| Pumped Storage |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
| Fuel Cells |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Renewable Sources |
0.7 |
3.1 |
3.1 |
3.1 |
3.1 |
3.2 |
3.2 |
3.2 |
3.2 |
| Total |
11.3 |
16.6 |
16.6 |
16.6 |
16.6 |
18.5 |
18.5 |
18.5 |
18.5 |
| Cumulative Unplanned Additions |
| Coal Steam |
0.0 |
16.0 |
13.3 |
10.4 |
9.7 |
46.4 |
32.1 |
16.8 |
34.8 |
| Other Fossil Steam |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Combined Cycle |
0.0 |
52.6 |
54.7 |
52.1 |
60.1 |
122.2 |
138.1 |
133.4 |
165.5 |
| Combustion Turbine/Diesel
|
20.2 |
111.1 |
119.1 |
127.3 |
125.1 |
151.2 |
154.5 |
163.1 |
176.7 |
| Nuclear Power |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Pumped Storage |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Fuel Cells |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Renewable Sources |
0.5 |
1.3 |
2.0 |
17.4 |
1.8 |
3.0 |
4.2 |
27.4 |
4.8 |
| Total |
20.7 |
181.0 |
189.1 |
207.3 |
196.7 |
322.7 |
328.9 |
340.7 |
382.0 |
| Cumulative Total Additions |
32.0 |
197.6 |
205.6 |
223.9 |
213.2 |
341.2 |
347.4 |
359.2 |
400.5 |
| Cumulative Retirements |
14.4 |
80.1 |
80.1 |
70.7 |
62.6 |
117.1 |
117.1 |
111.1 |
99.6 |
| Cogenerators |
| Capability |
| Coal |
7.1 |
7.5 |
7.5 |
7.5 |
7.5 |
7.7 |
7.7 |
7.7 |
7.7 |
| Petroleum |
1.0 |
1.1 |
1.1 |
1.1 |
1.1 |
1.2 |
1.2 |
1.2 |
1.2 |
| Natural Gas |
28.0 |
31.6 |
31.6 |
31.6 |
31.6 |
32.7 |
32.7 |
32.7 |
32.7 |
| Other Gaseous Fuels |
1.2 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
1.1 |
| Renewables |
5.8 |
6.5 |
6.5 |
6.5 |
6.5 |
6.6 |
6.6 |
6.6 |
6.5 |
| Other |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
| Total |
43.0 |
47.9 |
47.9 |
47.9 |
47.9 |
49.3 |
49.3 |
49.3 |
49.2 |
| Cumulative Additions |
8.1 |
12.9 |
12.9 |
12.9 |
12.9 |
14.4 |
14.3 |
14.4 |
14.3 |
| Source: Energy Information Administration,
Office of Integrated Analysis and Forecasting, National Energy Modeling
System runs nocomp.d010698a, aeo98b.d100197a, complo3.d031298b, and
comphiD3.d031398b. |
Table 20. Electricity Supply, Disposition, and Prices
(Billion Kilowatthours, Unless Otherwise Noted)
| Generation by Fuel Type |
| Electricity Generators |
| Coal |
1,758 |
2,014 |
2,007 |
1,987 |
2,050 |
2,282 |
2,190 |
2,073 |
2,277 |
| Petroleum. |
80 |
34 |
37 |
28 |
44 |
27 |
33 |
23 |
47 |
| Natural Gas |
288 |
628 |
671 |
618 |
714 |
1,034 |
1,171 |
1,088 |
1,373 |
| Nuclear Power |
675 |
643 |
643 |
698 |
643 |
480 |
480 |
553 |
480 |
| Pumped Storage |
(2) |
(3) |
(3) |
(3) |
(3) |
(3) |
(3) |
(3) |
(3) |
| Renewable Sources |
392 |
375 |
377 |
431 |
377 |
383 |
388 |
497 |
392 |
| Total |
3,191 |
3,691 |
3,732 |
3,758 |
3,824 |
4,203 |
4,258 |
4,230 |
4,566 |
| Nonutility Generation for Own Use |
26 |
26 |
26 |
26 |
26 |
26 |
26 |
26 |
26 |
| Cogenerators |
| Coal |
39 |
38 |
38 |
38 |
38 |
39 |
39 |
39 |
39 |
| Petroleum |
6 |
6 |
6 |
6 |
6 |
6 |
6 |
6 |
6 |
| Natural Gas |
174 |
192 |
192 |
192 |
192 |
201 |
200 |
200 |
200 |
| Other Gaseous Fuels |
7 |
7 |
7 |
7 |
7 |
7 |
7 |
7 |
7 |
| Renewable |
41 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
43 |
| Other |
3 |
3 |
3 |
3 |
3 |
4 |
4 |
4 |
4 |
| Total |
270 |
289 |
289 |
289 |
289 |
299 |
299 |
299 |
298 |
| Sales to Utilities |
121 |
125 |
125 |
125 |
125 |
127 |
127 |
127 |
127 |
| Generation for Own Use
|
149 |
163 |
163 |
164 |
163 |
172 |
172 |
171 |
171 |
| Net Imports |
38 |
38 |
33 |
36 |
36 |
27 |
27 |
29 |
29 |
| Electricity Sales by Sector |
| Residential |
1,079 |
1,252 |
1,258 |
1,265 |
1,296 |
1,443 |
1,449 |
1,449 |
1,593 |
| Commercial |
988 |
1,120 |
1,125 |
1,132 |
1,155 |
1,260 |
1,268 |
1,271 |
1,395 |
| Industrial |
1,014 |
1,164 |
1,186 |
1,199 |
1,206 |
1,306 |
1,343 |
1,316 |
1,363 |
| Transportation |
17 |
32 |
32 |
32 |
32 |
55 |
55 |
56 |
55 |
| Total |
3,098 |
3,568 |
3,601 |
3,628 |
3,689 |
4,064 |
4,115 |
4,091 |
4,406 |
| End-Use Prices (1996 cents/kWh) |
| Residential |
8.4 |
7.8 |
7.5 |
7.2 |
7.1 |
7.2 |
7.0 |
6.9 |
7.0 |
| Commercial |
7.6 |
7.1 |
6.8 |
6.4 |
6.4 |
6.5 |
6.1 |
6.0 |
6.2 |
| Industrial |
4.6 |
4.3 |
4.1 |
3.8 |
3.8 |
3.9 |
3.6 |
3.5 |
3.7 |
| Transportation |
5.2 |
5.1 |
4.7 |
4.5 |
4.5 |
4.8 |
4.3 |
4.3 |
4.4 |
| All Sectors Average |
6.9 |
6.4 |
6.1 |
5.8 |
5.8 |
5.9 |
5.6 |
5.5 |
5.7 |
| Price Components (1996 cents/kWh)
|
| Capital Component |
3.3 |
3.1 |
2.7 |
2.4 |
2.4 |
2.7 |
2.3 |
2.2 |
2.3 |
| Fuel Component |
1.2 |
1.0 |
0.8 |
0.8 |
0.8 |
1.1 |
0.6 |
0.6 |
0.6 |
| O&M Component |
2.0 |
1.9 |
1.7 |
1.7 |
1.7 |
1.8 |
1.5 |
1.5 |
1.4 |
| Wholesale Power Cost |
0.4 |
0.4 |
0.9 |
1.0 |
0.9 |
0.4 |
1.2 |
1.2 |
1.3 |
| Total |
6.9 |
6.4 |
6.1 |
5.8 |
5.8 |
5.9 |
5.6 |
5.5 |
5.7 |
| Source: Energy Information Administration,
Office of Integrated Analysis and Forecasting, National Energy Modeling
System runs nocomp.d010698a, aeo98b.d100197a, complo3.d031298b, and
comphiD3.d031398b. |
In the high fossil case, where capital costs are assumed to be recovered over
a shorter period, coal-fired capacity additions are about 6 gigawatts less in
2005 than in the no competition case. In this case, gas-fired additions are
about 22 gigawatts higher and are shared between turbines (14 gigawatts) and
combined-cycle plants (8 gigawatts). By 2015, coal-fired additions are almost
12 gigawatts less than in the no competition case, and gas-fired additions
are about 69 gigawatts higher. These changes in capacity additions indicate
that the assumptions about competitive markets used in this case have a
significant impact on fossil-fired capacity additions in the later years of
the projection period.
The low fossil competition case (where the RPS is imposed and nuclear
capacity is assumed not to be retired before operating licenses expire)
reduces the need for fossil-fueled plants even with a higher level of
electricity sales than in the no competition case. By 2015, coal-fired
capacity is about 30 gigawatts lower and gas-fired capacity is about 23
gigawatts higher than in the no competition case. As a result, coal-fired
generation is about 9 percent lower than and gas-fired generation is about 5
percent above the no competition case (Table 20).
It is interesting to note that the need for turbines is higher by about 12
gigawatts in the low fossil case compared with the no competition case
because the higher level of generation from nondispatchable renewable sources
requires that additional backup capacity be made available to meet peak
requirements. These cases indicate that natural gas is expected to have an
increasing share of electricity generation as demand levels grow and that
coal-fired generation will be lower than would occur in regulated electricity
markets, absent the assumption about additional demand growth under
competition.
Electricity trade levels across the NEMS regions change modestly across the
cases analyzed. Incentives for regional trade are driven by differences in
regional generation sources and region-specific characteristics. The
assumptions about increased transfer capability of the transmission network
in the low and high fossil cases do not cause trading patterns to change
because the cost differences are not sufficient to make trading economical.
This analysis does not address the potential changes in electricity trade
within a region that could occur in competitive markets.
Renewable Sources
Unless required by policies, the restructured electricity market is not
expected to stimulate central station renewable energy technologies. Overall,
the scenarios suggest that renewable sources will remain more costly than
fossil-fueled alternatives through 2015 and will penetrate electricity
markets further than they do in the reference case only to the extent
compelled, such as by an RPS that mandates generation from renewable sources.
The cases suggest that, if policies require increased use of renewable
sources, average electricity prices will increase slightly. Under the assumed
RPS (HR 655), most of the growth in renewable generation will be from
biomass, geothermal, and wind.
The results suggest that renewable sources will garner only a minor overall
portion of electricity supply under a range of electricity market conditions.
In the absence of an RPS, nonhydroelectric renewable sources (including
municipal solid waste) hold only a 2.4-percent share of total U.S.
electricity generation in 2015; the hydropower share falls as low as 6.6
percent (Figure 26). Although increased overall electricity demand also
raises generation from renewable sources, significant growth occurs only
under an RPS. Whereas generation by RPS-qualifying renewable sources
(biomass, geothermal, solar, and wind) is 74 billion to 76 billion
kilowatthours by 2005 and reaches as much as 85 billion kilowatthours by 2015
with no RPS, it increases to 130 billion kilowatthours in 2005 and to 190
billion kilowatthours in 2015 with an RPS (Table 21).
In the high fossil case, defined renewable sources remain barely changed from
their no competition case market share. If renewable sources are to expand
more rapidly, the results suggest a need for some significant market change,
such as accelerated improvements in renewable energy technologies, an RPS,
successful green pricing programs (where consumers choose electricity
suppliers based on their impacts on the environment), subsidies, or higher
costs for competing technologies.
|
Figure 26. U.S. Electricity Generation Shares by Energy Source,
2015
(Click graph to view full size)
|
Finally, the results suggest that renewable sources are highly vulnerable to
improvements in competing fossil- fuel technologies, as shown by the high
fossil case. Compared with the no competition case, renewable sources fare
about the same under competition absent a policy mandating higher shares.
The results also show the likely technology choices for expanded use of
renewable sources under more rapid growth or RPS conditions. Biomass, wind,
and geothermal are the likely "winners" among renewable energy
technologies. Biomass-powered generation increases most, more than doubling
from 46 billion kilowatthours in 1996 to 97 billion kilowatthours in 2015 in
the RPS case; its capacity also increases significantly, adding more than 7
gigawatts of new capacity by 2015. Geothermal generation increases from 16
billion kilowatthours in 1996 to 52 billion kilowatthours in 2015 in the RPS
case; its capacity also increases significantly, far more than doubling by
2015. Wind-powered generation also increases from 3 billion kilowatthours in
1996 to 38 billion kilowatthours in 2015, a leap of nearly 14 gigawatts of
capacity by 2015 in the RPS case. Because biomass capacity operates a much
greater proportion of the time than wind power and can compete in more
regions than geothermal, biomass-fueled generation appears the most likely
source for increased electricity generation under policies encouraging use of
renewable sources. However, significant issues of cost and land use could
arise if the growth of biomass becomes a reality (see Chapter 5).
Because they remain more expensive than both fossil and other renewable
alternatives, solar technologies are minor contributors in all the cases and
do not increase significantly. Further, because neither solar thermal nor
photovoltaic technologies operate as intensively as fossil technologies (they
have lower capacity factors), their contribution to total generation remains
small. The use of photovoltaic technologies could grow much more rapidly if
their cost declined or if electricity prices were higher than those projected
in this analysis.
Electricity Prices
Electricity prices are projected to decline from 1996 levels for all of the
cases analyzed, including the no competition case. Prices will decline even
in a "no competition" market because investments in new capacity
will be relatively modest compared with historical levels and because of
expected decreases in the price of coal. Prices in the competition cases are
further reduced due to improvements in the efficiencies of both plant
operations and the labor force. An additional factor contributing to lower
electricity prices in the competition cases is less construction of
capital-intensive coal plants (Table 20). In competitive markets, electricity
prices are expected to be sensitive to the price of natural gas because it is
projected to be used to meet demand during peak periods.
Electricity Fuel Consumption
In comparing the cases, EIA found that total energy consumption for
electricity generation essentially follows the overall demand for
electricity, although the composition of the fuel demands is important in
explaining differences. The AEO98 reference case has slightly higher
overall consumption in the electricity sector in 2005 than in the no
competition case, but the two cases are virtually the same in 2015 (Table
22), despite the fact that electricity demand in the AEO98 reference
case is higher by 51 billion kilowatthours in 2015, up from only 33 billion
kilowatthours in 2005 (Table 20). In part this reflects the lower
efficiencies for coal-fired generation. In the no competition case, the
assumptions with respect to the cost of capital provide an incentive for more
coal-fired and fewer gas-fired capacity additions than in the AEO98
reference case. Because of the lower efficiencies for coal-fired generation,
this translates into roughly the same consumption in the two cases in 2015,
despite the higher demand in the AEO98 reference case. The tradeoff
between coal and natural gas in the two cases leads to a slightly higher
efficiency in total electricity production in the AEO98 reference
case.
Table 21. Renewable Energy Capacity and Generation
| Net Summer Capability (Thousand Megawatts)
|
| Electricity Generators |
| Conventional Hydroelectric
|
78.58 |
80.65 |
80.65 |
80.65 |
80.65 |
80.71 |
80.71 |
80.71 |
80.71 |
| Geothermal |
3.02 |
2.93 |
2.93 |
4.28 |
2.95 |
2.72 |
2.87 |
7.73 |
3.22 |
| Municipal Solid Waste |
2.91 |
3.46 |
3.46 |
3.46 |
3.46 |
4.26 |
4.26 |
4.26 |
4.26 |
| Wood and Other Biomass
|
1.91 |
2.02 |
2.02 |
3.98 |
2.02 |
2.02 |
2.28 |
8.66 |
2.53 |
| Solar Thermal |
0.36 |
0.38 |
0.40 |
0.38 |
0.38 |
0.48 |
0.51 |
0.49 |
0.48 |
| Solar Photovoltaic |
0.01 |
0.08 |
0.08 |
0.38 |
0.08 |
0.38 |
0.38 |
0.68 |
0.38 |
| Wind |
1.85 |
2.68 |
3.31 |
15.19 |
3.18 |
2.96 |
3.68 |
15.36 |
3.79 |
| Total |
88.64 |
92.20 |
92.86 |
108.30 |
92.72 |
93.54 |
94.69 |
117.90 |
95.37 |
| Cogenerators |
| Municipal Solid Waste |
0.41 |
0.45 |
0.45 |
0.45 |
0.45 |
0.47 |
0.47 |
0.47 |
0.47 |
| Biomass |
5.41 |
6.05 |
6.06 |
6.06 |
6.06 |
6.09 |
6.08 |
6.11 |
6.07 |
| Total |
5.81 |
6.50 |
6.50 |
6.51 |
6.50 |
6.57 |
6.56 |
6.58 |
6.55 |
| Generation (Billion Kilowatthours)
|
| Electricity Generators |
| Conventional Hydroelectric
|
346.30 |
318.10 |
318.20 |
318.20 |
318.20 |
318.70 |
318.80 |
318.70 |
318.90 |
| Geothermal |
15.70 |
17.34 |
17.34 |
26.76 |
17.45 |
16.87 |
17.92 |
51.96 |
20.38 |
| Municipal Solid Waste |
18.85 |
23.13 |
23.14 |
23.14 |
23.14 |
28.67 |
28.68 |
28.67 |
28.70 |
| Wood and Other Biomass
|
7.27 |
9.48 |
9.48 |
23.17 |
9.48 |
9.48 |
11.24 |
55.93 |
13.02 |
| Solar Thermal |
0.82 |
0.96 |
1.04 |
0.98 |
0.96 |
1.30 |
1.39 |
1.32 |
1.30 |
| Solar Photovoltaic |
0.00 |
0.20 |
0.20 |
0.94 |
0.20 |
1.00 |
1.00 |
1.75 |
1.00 |
| Wind |
3.17 |
5.98 |
7.70 |
37.68 |
7.39 |
6.88 |
8.86 |
38.13 |
9.20 |
| Total |
392.11 |
375.20 |
377.10 |
430.80 |
376.80 |
382.90 |
387.80 |
496.50 |
392.40 |
| Cogenerators |
| Municipal Solid Waste |
2.09 |
2.22 |
2.22 |
2.22 |
2.22 |
2.34 |
2.34 |
2.34 |
2.34 |
| Biomass |
39.17 |
40.46 |
40.48 |
40.52 |
40.49 |
40.61 |
40.55 |
40.72 |
40.47 |
| Total |
41.25 |
42.68 |
42.70 |
42.74 |
42.71 |
42.95 |
42.89 |
43.06 |
42.81 |
| Source: Energy Information Administration,
Office of Integrated Analysis and Forecasting, National Energy Modeling
System runs nocomp.d010698a, aeo98b.d100197a, complo3.d031298b, and
comphiD3.d031398b. |
In the low fossil case, coal consumption is lower by almost 2 quadrillion Btu
in 2015 compared with consumption in the no competition case. Consumption of
renewable and nuclear fuels is higher based on the assumptions used in the
low fossil case, and natural gas consumption is about the same as it is in
the no competition case. In the high fossil case, both coal and gas
consumption are higher in 2015 than they are in the no competition case in
2005, but by 2015 coal consumption is about the same as it is in the no
competition case. Natural gas consumption is about 2 quadrillion Btu greater
because of higher electricity demand levels.
The average price of fuel used for electricity production in 2015 is
projected to be about the same as in 1996 in all but the high fossil case
(Table 22). In the high fossil case, an increase of about 11 percent in the
average price is projected because of higher natural gas prices resulting
from assumed higher drilling costs for onshore production. Natural gas prices
increase slightly in the other cases but are offset by an almost 30-percent
decline in coal prices between 1996 and 2015.
Table 22. Energy Consumption and Prices for Electricity
Generation
| Energy Consumption by Electricity Generators
(Quadrillion Btu per Year) |
| Distillate Fuel |
0.08 |
0.07 |
0.07 |
0.07 |
0.08 |
0.07 |
0.07 |
0.07 |
0.09 |
| Residual Fuel |
0.67 |
0.28 |
0.30 |
0.22 |
0.36 |
0.20 |
0.25 |
0.16 |
0.37 |
| Petroleum Subtotal |
0.75 |
0.34 |
0.37 |
0.28 |
0.44 |
0.27 |
0.32 |
0.23 |
0.46 |
| Natural Gas |
3.04 |
5.39 |
5.69 |
5.23 |
6.01 |
7.98 |
8.71 |
8.02 |
10.06 |
| Steam Coal |
18.36 |
20.60 |
20.55 |
20.35 |
21.04 |
23.16 |
22.29 |
21.21 |
23.21 |
| Nuclear Power |
7.20 |
6.87 |
6.87 |
7.45 |
6.87 |
5.12 |
5.12 |
5.90 |
5.12 |
| Renewable Energy |
4.45 |
4.37 |
4.37 |
5.06 |
4.31 |
4.44 |
4.53 |
6.25 |
4.59 |
| Electricity Imports |
0.39 |
0.39 |
0.34 |
0.37 |
0.37 |
0.28 |
0.28 |
0.30 |
0.30 |
| Total |
34.20 |
37.96 |
38.19 |
38.75 |
39.03 |
41.25 |
41.26 |
41.91 |
43.75 |
| Energy Prices to Electricity Generators by
Source (1996 Dollars per Million Btu) |
| Fossil Fuel Average |
1.54 |
1.46 |
1.49 |
1.44 |
1.51 |
1.49 |
1.60 |
1.51 |
1.71 |
| Petroleum Products |
3.27 |
3.61 |
3.57 |
3.76 |
3.46 |
4.13 |
4.00 |
4.27 |
3.77 |
| Distillate Fuel |
4.90 |
5.17 |
5.16 |
5.15 |
5.14 |
5.45 |
5.47 |
5.42 |
5.40 |
| Residual Fuel |
3.07 |
| |